Assignment title: Information
lnstructions
Please submit your answers via electronic submission on Moodle in Word (.doc or ",,.
.docx) or PDF format. Please ensure that your name and student number are written
on the document itself.
NB there is no need for a bibliography. All appropriate references should appear in
the text of each answer (in the OSCOLA format) and should be cases, legislation or
clauses from the JCT contract only. lf you choose to use direct quotations, you must
also explain in your own words in order to benefit from marks.
The assignment
This assignment consists of 2 parts; please answer them both as succinctly but
comprehensively as possible, with np more than 1500 words for the whole
assiqnment.
Part 1.
Apple Construction Ltd received a letter from Green Bay Developments limited:
Dear Sirs
$ubject to contract
Thank you for your tender dated 12 February 2016, regarding the
construction of 26 detached and semi-detached dwellings at
Green Bay, North Greenwich.
We would like you to start work immediately and to engage subcontractors and suppliers in order to meet our planned eompletion
deadline of April 2017. We do, however, reserve the right to stop
work at any time.
We shall be in contact shortly to finalise the contract.
Yours faithfully
Green Bay Developments Ltd
Chris, the project manager for Apple Construction, fonrvards the lefter to Mohammed,
the main contractor for Apple Construction and asks Mohammed to engage subPage 1 of2