Assignment title: Information
PROJECT CASE: ROLLER COASTER SAFETY PROJECT Background
Super Wonderland (SWL) Pte Ltd in Singapore belongs to the USA's Wonder Group (WG),
one of the world's largest entertainment companies with businesses in movies, theme
parks and resorts. SWL operates a theme park on Coney Island. It aims to provide a full
range of fun family activities for visitors to enjoy. Its motto is "We make your day Super
Wonderful!" SWL has been successful in bringing many innovative entertainments and
theme rides to Singapore, which attracted locals and tourists from the region.
Recently, roller coaster safety has been an issue for several theme parks.
(Ref: Riders rescued from Universal Studios' Battlestar Galactica ride after it stops due to
'technical error' http://www.straitstimes.com/singapore/riders-rescued-from-universalstudios- battlestar-galactica-ride-after-it-stops-due-to)
Hence, the Government Safety Regulation Board (SRB) has tighten the regulations and
ordered a re-examination of all the roller coasters in the country. One of SWL's main
attractions, Sky Rock Roller Coaster, was found to have potential faults. It was ordered to
stop for operations until the faults have been rectified. It is imperative for SWL to solve the
problems completely to ensure public that is a safe for enjoyment. The management
decided to embark on this project called the Roller Coaster Safety (RCS) Project.
Section 1: Defining the Project
The CEO, Jack Ng, has appointed the following staff to form a project team for the RCS
Project:
1. Yourself, a Senior Executive who is appointed as the Project Manager. You have
managed a few projects successfully in SWL. The management trusts that your
resourcefulness and tenacity will help in this important project.
2. Mr. Hashim, a Senior Engineer from the Ride Operations: He has knowledge in roller
coaster operations. His scope of work includes supervising subcontractors to install
and test the roller coaster system.
3. Mr. Lim KK: Facility Manager: He is in charge of the theme park infrastructure and
facilities other than ride and roller coaster systems.
The Sky Rock Roller Coaster was implemented seven years ago by Wagon Pty, which is
now defunct. To rectify the problems, SWL will have to seek consultancy from Tron AG
from Germany, a major theme ride supplier to the WG Group. The reinforcement of the
Sky Rock's structure will also be subcontracted to Tron AG, supervised by Hashim.
The CEO briefed you on the management's expectations: The project shall start on 1
September 2016. All the SRB's new safety requirements must be fully complied. Although
SRB set a deadline for the roller coaster to be certified and relaunch by 30 Dec 2016, the
management wish this can be done by 22 Dec 2016, as prolonged closure will leave public
a bad image of SWL. Exact budget has yet to be worked out. Finance is tight, but if the
project team can justify essential expenses, management will try to accommodate.
Question 1
(a) Based on the CEO's direction, you are to appraise the priority of the project by
constructing a project priority matrix. (5 marks)
(b) Appraise four (4) relevant conditions in deciding to use the Top-down or Bottom-up
Estimate approach for estimating the project cost. For each condition, explain the
preferred approach and whether the approach is suitable to SWL for RCS Project.
Recommend the overall best approach and explain one estimation cost method to
SWL.
You shall answer in this format:
For condition on ________, *Top-down/Bottom-up Estimate is preferred because
____________________. This *is/is not the case for RCS Project as
____________________. Hence SWL shall use *Top-down/Bottom-up Estimate under this
condition.
Overall, I recommend SWL to adopt the _____________ approach. The method of
estimation will be ___________. [Briefly explain the method]
(12 marks)Section 2: Managing the Project Team Question 2
SWL will contract the consultancy to Tron AG. The reinforcement of the Sky Rock's
structure will also be outsourced to Tron AG implementation team, supervised by the
project member, Hashim. Tron AG's performance will have a major impact on the success
of the RCS Project.
(a) Examine two (2) advantages of outsourcing the works mentioned above to Tron AG
(4marks)
(b) Analyse and discuss how you can adopt three (3) relevant best practices in
outsourcing project work to manage Tron AG. (9 marks)
Section 3: Scheduling Resources and Costs
You conducted a pre project discussion with Hashim and Lim. The team worked out the
project activities and preliminary details as shown in Table 1. Furthermore, using the
Budget Estimate approach and method you recommended in Q1(b), the budget shown in
Table 2 is granted by SWL management.
Table 1: Activities List for Roller Coaster Safety Project
#Table 2 – Budgeted Cost
#
Note on using MS Project for Questions 3 & 4:
You have to use MS Project to plan and track the RCS Project in Question 3 & 4. Take
note of the following and carry out the steps.
1. The above schedule and costing are based on a 5-day work-week. Each day has 8
working hours. No work will be performed on Saturday, Sunday and Public Holidays
unless stated otherwise. Do not change any durations, predecessor relationships or
the resources assignments.
2. The Public Holidays which may fall into the project period and are to be marked as
Non- Working Day are: Hari Raya Haji on 12 Sep 2016, Deepavali on 29 Oct 2016,
Christmas on 25 Dec 2016 and New Year on 1 Jan 2017. If a Public Holiday falls on
Sunday, the next day (Monday) will be a holiday-in-lieu. However, there will be no
holiday-in-lieu for Public Holiday on Saturday.
To set Non-working day, click Project->Change Working Time. In the pop up
window, enter the holiday into the table, click Details, and then click Nonworking).
3. Enter the Task Name, Duration, Predecessors and Resource Names into the
respective columns in MS Project. Do not change the order of the activities (you are
not required to list according to WBS).
Set Activity 1 as the Higher Level Activity. Right indent all other activities below to
second level. Click Project -> Project Information -> Set Start Date as 1 Sep 2016.
Then
Right click on Activity 1 to access its Information. Set its Deadline under Advance
Tab as 22 Dec 2016
4. Enter the costs and accrual methods shown in Table 2 into Fixed Cost cells in the
MS Project Cost Table (View-> Table -> Cost to access Cost Table).
5. Diagrams, charts, tables, graphs and relevant project outputs may be shown as
images in answers to Questions 3 & 4. These must be appropriately cropped and
presented so that they are legible and can be viewed clearly and legibly. The
answers shall not refer the examiner to open and view contents of any inserted
files. Such reports will appear unprofessional and deem to have not answered with
0 mark awarded on the related questions.
Question 3
(a) Prepare and present in a single diagram, the Gantt Chart view of MS Project with
columns shown for Information, Task Name, Duration, Start Date, Finish Date,
Predecessors and Resource Names. State the project completion date and any
resource conflicts observed.
(6 marks)
(b) Due to the specialised skills required, tight project schedule and full dedication of
the team required in this project, resource conflicts cannot be solved by transferring
the task to other people, multi-tasking or adding in more manpower. Hence they can
only be resolved through resource leveling.
You are mindful of the management's wish to minimise the project duration. Hence
you must first perform a resource levelling within the schedule. Carry out the
following steps:
Click Resource-> Leveling Option -> check the button Level, enter the dates: From
1/9/2016; to 22/12/2016, then check the box: Level only within available slack.
Finally click Level All.
Evaluate and discuss the changes and any effect due to this resource leveling
operation. Determine any impact to the project completion date (i.e. Finish Date of
Activity 1). (4 marks)
(c) You are also aware of the need to fully meet the new safety requirements, and
hence no reduction of work scope is allowed. For any resource conflict that cannot
be solved within the original schedule, perform a resource levelling beyond the
deadline. (Carry out the same steps in Q2(b), except uncheck the box: Level only
within available slack).
Discuss the changes and any effect due to this resource leveling operation. State
what you observe on MS Project and any new project completion date. (4 marks)Section 4: Baselining and Tracking Project
The CEO approves the new completion date evaluated in Q3(c). You must change the
deadline for Activity 1 to the new completion date.
Set the Status Date (Project -> Status Date) as 1 Sep 2016. Save the updated MS Project
as Baseline Plan (Project -> Save Baseline -> check Entire project), which will be used to
evaluate the project performance at a later stage.
Question 4
The project progresses on. Several issues occurred during the implementation period:
(1) Due to the appreciation of the Japanese Yen, the motor cost (Activity 4) increased
by 5%.
(2) The entrance to the worksite (Activity 6) was found to be too small. Enlargement
has to be made with additional cost of $4000. Luckily this does not affect the
schedule.
(3) You negotiated with Tron AG (Activity 3). They agreed to give a 10% discount on the
consultancy fee.
(a) Modify the Fixed Cost cells in the Cost Table to incorporate the above changes.
(i) There is an addition change: Due to additional customisation, upgrade of motor
(Activity 9) needs five (5) more days. The subcontractor agreed to work with Hashim
over weekends when absolutely necessary at the cost of $1000 per Saturday, Sunday
or Public Holiday, and $500 per weekday. Noted the deadline set by the Safety
Regulation Board, evaluate the number of Saturday, Sunday and or Public Holiday, and
additional weekdays that Activity 9 has to be carried out with minimum additional cost.
Explain your approach and state these additional working days and the additional cost.
Add the cost and days to Activity 9.
Note: In order not to affect other activities' schedule, you have to modify only Hashim
working day for the weekends.
Do this by:
View->More View->Resource Sheet -> Right Click on row Hashim- >Information-
>Change Working Time. In the table, enter the weekend dates, then click Details, then
click Working Times, click both the morning and afternoon. (5 marks)To move the project forward, the CEO approved all the changes. The project
progresses and it was re-launched on the date in your final plan.
Set the Status Date to the next working day after the roller coaster launch date. Update
the project (Project -> Update Project -> Entire Project).
(ii) Present in a single diagram the Tracking Gantt Chart view of MS Project with
columns shown for Task Name, Duration, Start Date and Finish Date. State the
completion date. (5 marks)
(iii) State the Cost Performance Index (CPI) formula, and evaluate the CPI. Present a
MS Project cost report or table with CPI to verify the correctness of your calculation.
Analyse and interpret the CPI.
(b) Propose three (3) actions that could have been done earlier to prevent the issues in
Question 4(a) from happening or mitigate their impacts.
SECTION B (Total 25 marks)
The Senior Management of SWL asked for a presentation one week after the Sky Rock
roller coaster relaunch. It should address the following issues:
1. What are the objectives and priorities of the project, and are they met?
2. Were there changes in schedule and what are the contributing events?
3. Was there a cost overrun and what were the contributors for the cost overruns if
any?
4. Lessons learnt and suggestions for future project.
25 marks