Assignment title: Management
9.0 selection of preferred alternative
9.1 Trunk ewer Alignment
The initial evaluation if alternatives resulted in the selection of Route DS4 and US2 as the
overall recommended alignment (figures 6 and 9), as was presented at the second public meeting
(June 27, 2007).
Through the public consultation process it became apparent from the "friends of Stoney creek",
that additional details were required before they could support the US2 portion of the option. The
group felt that the environmental assessment needed to address issues relating to the construction
of a trunk sanitary sewer within the ESA area located west of Highbury Avenue and north of
Stoney Creek. Concern was expressed with respect to both short and long term impact to the
ESA area and the potential benefit of mitigation/compensation measures. In addition, the group
wanted to ensure that section 15.3.3 of the Official Plan was upheld which indicates that as a
condition of approving infrastructure projects in natural heritage areas, the city may require
specific mitigation and rehabilitation measures and/or compensation for the damage to naturel
features and functions caused by construction or maintenance of the infrastructure.
As such, additional environmental evolution of the preferred option was deemed necessary to
father assess impacts and required mitigation, rehabilitation and/or compensation measure. In
general, the additional investigations and reassessment of mitigation measure of option US2
consisted of the following:
1. The portion of US2 located just east of the Stackhouse avenue crossing was further
investigated with respect to slope stability. Golder associates outlined in their letter dated
November 5, 2007 (see appendix B) that there were no adverse impacts to either the
future sewer or the existing slopes in the area with respect to slope stability issues.
2. A floral life science reconnaissance along US2 was completed to ensure any atypical
species would not be impacted. (If atypical species were identified an appropriate
mitigation plan was to be required.)
3. Tree protection zones would have to be established at or beyond the drip line of all trees
to be maintained.
4. Overhanging branches that may be impacted from construction equipment activity would
require trimming.
5. Silt fencing was recommended around stockpiles adjacent to woodlands.
6. A replanting strategy was recommended where possible.
7. A qualified hydrogeologist was to make recommendations during detailed design and
construction in order to ensure that baseflows to waterways were not impacted.
8. During construction it was to be ensure that mitigation and/ or compensation was
provided in accordance with the city of London policies in place at the time.
9. A replanting strategy was recommended where possible.
10. A qualified hydrogeologist was to make recommendations during detailed design and
construction in order to ensure that baseflows to waterways were not impacted.
11. During construction it was to be ensured that mitigation and/or compensation was
provided in accordance with the City of London policies in place at the time.
The UTRCA provided a comment that it preferred to have the new Stackhouse Avenue
construction / flood control facility coordinated with the new sanitary sewer construction in order
to avoid disturbing the creek corridor more than necessary. As noted in Section 5.2 of this report
trenchless construction was not considered feasible along any portion of this section due to the
type of soil. Therefore in consideration of this comment and the soil conditions, it was
determined in 2008 that the EA was far enough along with the presentation of the recommended
options that the installation of a casing at this crossing would not change the outcome of this EA.
Therefore a 1050m dia. Concrete casing was installed on the upstream side of the Stackhouse
Avenue crossing in 2008 in order to facilitate the installation of the sanitary sewer at some point
in the future. Figure 14 shows a detail of the sanitary crossing concept.
The potential of installing a watermain at the Stackhouse Avenue crossing was also considered,
however it was determined by the City that the water distribution network did not require a
linkage at this location.
Following these investigations, the City decided to defer finalizing this EA pending the update of
the City's Official Plan policy of section 15.3.3 regarding construction within environmentally
sensitive areas. As a result of this update, the City had Deican prepare an "Environmental Impact
Study (EIS) for the Stoney Creek Trunk. Sanitary sewer and Warermain CROSSING Class EA,
"dated March 2010 to assess mitigation and compensation options for the routing through an
ESA as a result of the various mitigation and compensation options for the routing through an
ESA as a result of the carious mitigation and compensation measures required as part of the EIS,
updated costing, and timing implications of developments the preferred alignment was chosen as
US4 and DS5 as shown on Figure 13.
9.2 Rationale for the selection of route US4/DS5 as the recommended Alternative:
Route US4
1. Potential to service a portion of Marsman lands;
2. Low to moderate construction costs; represents an effective use of capital;
3. Shallow sewer allows for ease of construction/ less disturbance;
4. Timing of Marsman development coincides with sewer construction plans;
5. Avoids creek corridor and ESA;
6. Ease of construction;
7. Availability of property;
Route DS5
1. Avoids Natural Environment disturbance along the creek banks;
2. Minimizes the number of creek crossings required;
3. Least construction impact with respect to disturbance behind existing homes, especially
homes with foundation settlement issues in the past;
4. Public prefers construction along existing streets rather than along creek corridor;
5. Low to moderate construction costs; represents an effective use of capital;
6. Good flexibility with respect to servicing future development areas;
7. Ease of construction;
8. Availability of property;
9.3 Implementation
One of the key concerns expressed by the development community was a desire to expedite the
implementation of the construction of the critical downstream section. Subject to final budgetary
approval, the City advised that it is intended to proceed with the construction of the downstream
section (DS5) as a capital project with construction in 2011. A major portion of the upstream
section (US4) wold be located within a development block located south of Stoney Creek and
east of Stackhouse Avenue. It will be necessary to coordinate with affected property owners the
means by which trunk sanitary sewer will be constructed within future road allowances.
The sections of the trunk sanitary sewer along Highbury Avenue south of Stoney Creek will be
coordinated with road improvements. The crossing of Stoney Creek will be done trenchlessly.
Sections of the trunk sanitary sewer north of Stoney Creek would be carried out in the future.