Assignment title: Management
CPCCBC5005A: Assessment 4
What you have to do
Complete two of the following three parts (i.e. complete Part 1 and Part 3, or, complete any
other combination of two parts). Do not complete more than two parts as any additional parts
submitted will not be marked.
This is an ungraded assessment, and your submission will be assessed as Competent or
Not yet competent
When doing this assessment make any assumptions you need, but be sure to state what
you have assumed at the beginning of each part of your assessment.
Most Parts of this Assessment relate to the following Project:
19735 Project Medium Rise Apartments
Job Address: 2135 The Boulevard, Strathfield, NSW
Job Title: Proposed Commercial and Residential Development
Client: AKM Developments
Architect: Olympic Designs, 55 Olympic Pde, Homebush, NSW
You should obtain the following documents for the job, from the Learning resource tab for
the unit on the OLS:
Plans: 16 pages
Bill of Quantities: 6 pages
Specification of Works: 60 pages
Task
Part 1
Assume you are the site manager in charge of the construction of the Strathfield apartments
with the above documentation, and that it has been decided to use AS4000 as the standard
form contract for the project, and AS4901 as the subcontract. Obtain a copy of AS4000 &
AS4901. You can download a copy from Saiglobal using the online TAFE library access
method described on the OLS Course information page. Also obtain the construction
schedule for the project - this was provided in the assessment for unit CPCCBC5002A –
refer to the OLS Assessment information link for the unit if you need a copy.
• Review the collected documents, and identify what subcontractors you need to build
the project.
LA018492 Assessment 4 CPCCBC5005A Ed 1 1
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014You need to familiarise yourself with the project to do this. This involves inspecting each plan
briefly – as a minimum inspect each plan for a minute or so initially to see what it contains,
and the general arrangement. Also briefly review the BoQ and specification.
a. Prepare a list of subcontracts that you will need for the project, and then order the list
into your preferred construction sequence. Use this list to create a call forward
sheet for the project which you need to submit for marking. A call forward sheet
template is provided in the Assessment information link. Determine and show on the
call forward sheet the work day number that each contractor is required to
commence on site - i.e. Day 5, Day 20 etc. - do not use dates. Also assume that
work starts on site on Day 1. Clearly describe on the call forward sheet what items of
work this contractor is to do. When determining the subcontractors required, make
sure you identify any requirements for specialist skills, requirements or
competencies, and note these on the call forward sheets. Do not fully complete other
aspects of the call forward sheet.
b. Use all relevant information you have collected to develop a formal organisation
layout for the project – this should show how you would structure the labour on the
project and include both labour for direct employees and subcontractors. Note your
structure needs to conform to requirements of AS4000 contract conditions, and
should assume that the principal will supply plans and specification but not a Bill of
Quantities to the contractor (AS4000 Clause 8.3) A simple example management
structure for a project that includes both design and construction is shown in Figure 1
below.
c. Prepare a list of special conditions of contract that you would want to use with
subcontractors on the project. Assume that you intend to use AS4901 as your
subcontract generally on the project. (AS4901 is a companion document specifically
prepared to be compatible with AS4000.) Consider whether to include or omit for
example coverage in the following areas:
• WHS
• Environmental planning
• Industrial relations
• Co-ordination of works
• Quality
• Prior works
• Protection of works
• Programming i.e. clause 33 of AS2545
• Dispute resolution
• Services to be provided by contractor in relation to materials handling,
crane, man and material hoist, toilet facilities and power and on which level.
i.e. is Subcontractor responsible for unloading trucks, and the provision of
any site sheds etc.
• Back charges
• Insurance
• No further claims clauses – i.e. at the end of job, or within 21 days or forfeit
• Contractors right to dismiss – i.e. contractor retains the right to dismiss
employees from site for reasonable cause, or for any cause the builder
considers reasonable, or at the builders discretion, with a requirement for
arbitration, and whether to include safety, non-performance etc.
• Novation or assignment of subcontract
• Contractor power to vary or omit works – i.e. contractor can vary
• Essential services certificates – i.e. subcontractor to provide essential
services certificates for work completed prior to any termination
• Prior work - i.e. the subcontractor is deemed to accept the adequacy and
completeness of the prior work as soon as he commences work on the prior
work, and make no claims for variations for the inadequacy of prior work.
2 LA018492 Assessment 4 CPCCBC5005A Ed 1
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014(i.e. subcontractor can issue non-conformance certificates as part of their
QA process.
• Termination for convenience
d. Submit each item above to complete this part, namely submit Items a, b & c being
the call forward sheet, and formal contractor / subcontractor structure, and the
special conditions of contract for this part of your assessment.
LA018492 Assessment 4 CPCCBC5005A Ed 1 3
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014e.
Waterproofer
Tiler
Plasterer
General
Forman
Forman
Services
& Facade
Forman
Forman Finishes
Structures
Leading
Hand
Leading
Hand
Leading
Hand
Client Project
Manager
Head
Contractor
Design
Team
Direct
Workforce
Sub
Contractors
Formwork
Reinforcement
Concreter
Masonry
Excavation
Electrical
Fire
Mechanical
Hydraulic
Lift
Crane
Hoist
Structural
steel
etc etc
Joinery
Fire door
Metalworker
Carpenter
Curtain walls
Door/window
Landscaping
Renderer
Painter
Glazing
Paving
Access
4 LA018492 Assessment 4 CPCCBC5005A Ed 1
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014Part 2 Select subcontractors
In this part you need to compare and evaluate subcontract quotations for formworker and
concretor work and determine which should be used on the Strathfield Apartment project.
You are to assume that you are the Project Manager for the multi storey unit development
and your program requires you to let the subcontract for CONCRETE and FORMWORK for
the project urgently.
You elect to use a Dincel reinforced concrete wall system instead of basement block walls
shown for its speed advantage.
You have received the attached four (4) quotations from the purchasing officer for the
works. Analyse and compare these quotations by comparing them with your original
tender budget for this work and decide which is the most cost and time effective so
that a sub contract can be raised.
All the subcontractors have successfully done work for your company previously and are
deemed equally proficient as each other to effectively carry out the specified works.
Liquidated damages on the project are $4,500 per day. Builder's site O/H costs are $2,000
per day. Assume all activities are programmed on the critical path.
Use the following tender budgets for your comparison.
ESTIMATOR'S TENDER BUDGET INFORMATION:
Concretor Package No.1
Supply, place and finish reinforced 32MPa concrete and associated formwork and falsework
supports to basement floor slabs, ramps and dincel walling up to and including the level 1
floor slab. (Note: waste is included in $ rates but not in measured quantities)
- Total concrete volume (excluding waste) 527m3
• Basement slabs beams and columns 305m3
• Ramps between basement slabs 57m3
• Dincel reinforced concrete walls 165m3
- Total contact surface areas:
• Slab on ground 684m2
• Suspended slabs and ramps from basement to level 1 1,310m2
a. Formwork and falsework to suspended slabs, beams & columns
b. = 1,310m2 x $100/m2$131,000
c. S&P reinforcement = 150kgs/m3 x 527m3 x $2,200/tonne – takes 15 days $173,910
d. Supply conc. for slabs beams col. walls incl. waste 527m3 x $205/m3 $108,035
e. Cost to place conc. to slabs, beams, columns & walls 527m3 x $35/m3 $18,445
f. Cost to finish slabs and ramps 1930m2 x $5.85/m2 $11,302
g. Supply concrete pump/s (12 setups i.e. 12 x $1,000) $12,000
h. Allowance for concrete testing $3,300
i. Termite control = 684m2 @ $5.20/m2 $3,557
j. S&P 50mm sand blinding = 684m2 @ $3.80/m2 $2,600
k. Supply 50mm sand blinding = 684m2 @ $1.80/m2 see above
l. Supply 'Fortecon' membrane = 684m2 @ $1.97/m2 $1,347
m. 'Fortecon' membrane /m2 place only = 684m2 @ $5.90 $4,036
n. Chemically cure slab = 1,368m2 @ $2.65/m2 $3,625
o. Allowance for rubbish removal $2,000
p. Hoisting allowance for concretor/formwork/steelfixers $6,000
q. Sheds allowance as supplied by Builder $2,000
LA018492 Assessment 4 CPCCBC5005A Ed 1 5
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014Total Concretor trade budget $483,157
Note: Formwork and falsework cost above includes to S&P Dincel. Concrete includes a
waste allowance of 5% on measured quantity from drawings. Reinforcement quantity of
150kgs/m3 concrete is the theoretical reinforcement quantity, and a rolling margin of +5% is
to be expected if trucks loads are weighed.
It is estimated that 12 concrete pump setups will be required to complete the works.
A normal working day is deemed to be from = 7am to 3.20pm and includes 20 mins extra
per day to accumulate a rostered day off once every 4 weeks. The work is expected to take
65 working days.
6 LA018492 Assessment 4 CPCCBC5005A Ed 1
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014Ultimate Concrete Services Pty Ltd
21 Foundry Road, Penrith NSW 2751
Phone: (02) 88667733
Facsimile: (02) 88667734
ACN: 654 321 557
Contractor Licence: 222 111 555
Quality Concreting and Formwork Services for the Construction Industry
11th September, 2014
The Manager
Best Constructions Pty Ltd
52 Pearl Street,
Liverpool NSW 2170
Attention: John Smith
Dear John,
Re: Job No. 09/14 - 2135 The Boulevarde, Strathfield
· Concrete & Formwork Tender.
In reference to your invitation to tender dated the 20th August 2014 for the above project,
we hereby submit details of our lump sum prices to carry out these works.
Complete reinforcement and concrete works on a supply place and finish basis to all
concrete slabs, beams, columns and walls (including Dincel basement walls) from
basement to and including level 1 slab, but excluding formwork = $305,520
All necessary formwork requirements = $92 /m2
(surface contact area of concrete to be measured on stripping).
Our day labour rate is $68 /hr normal hours.
Our tender includes the following items as requested:
• all necessary testing as per code
• supply and place membrane
• place only sand blind, material supplied by others
• all termite treatment, as per specification
• removal of all rubbish generated off the site
• all concrete pumping; up to eight (8) setups, additional setups $750 ea.
• estimate time to complete is 70 working days.
Builder to supply the following:
• all lunch, change & toilet facilities in accordance with union requirements
• all hoisting facilities, except concrete placement
• curing concrete surfaces
Our quotation is valid for a period of 30 days from the date of this quotation.
Yours sincerely,
Anthony Blanski, Manager
LA018492 Assessment 4 CPCCBC5005A Ed 1 7
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014Professional Formwork and
Concreting Services Pty Ltd
Offering the Builder a complete concreter trade
20.years of services to the industry
Unit 5/41 Barry Crescent, St Leonards NSW 2067
Phone: (02) 9555-2367 Facsimile: (02) 9555-2366
ABN: 34543362155 Contractor Licence: 7548623
15th September, 2014
The Manager
Best Constructions Pty Ltd
52 Pearl Street,
Liverpool NSW 2170
Attention: John Smith
Dear Sir,
Re: Job No. 09/14 - 2135 The Boulevarde, Strathfield
Formwork & Concrete quotation
With reference to your invitation to tender dated the 20th August 2014 for the above
project, we hereby submit our tender subject to Rise & Fall as per 'NCAP2 formula.
Concrete testing $8 m3
Place only and finish concrete slabs $48/m3
Concrete pump setups $500 / setup
Termite control $6.00 /m2
50mm sand blinding (supply and place) $4.30 /m2
Place only membrane, supplied by others: $7.00 /m2
Supply, place and strip formwork: $110.00 /m2
Note: Concrete is to be supplied by others, no steel reinforcement or curing of concrete
allowed.
Our rates include removal of any rubbish generated from these trades and hoisting of
materials. To assess the total concrete quantities, we require payment on the basis of
concrete truck delivery dockets. Builder to supply shed accommodation for workers.
Our rates are subject to Rise & Fall from the date of this quotation. This quotation is
valid for a period of 60 days.
Our estimation of time to complete these works is 53 working days, provided other
trades are carefully coordinated. Day labour, if required is $70 /hr normal working hours.
Assuring you of our closest cooperation expediting this project.
Yours faithfully,
Frank Nassif
Director
8 LA018492 Assessment 4 CPCCBC5005A Ed 1
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014Quality Concreting Pty Ltd
We always meet the quality mark
62 Wentworth Avenue, Thornleigh NSW 2120
Phone: 9555-3434 Facsimile: 9555-2626
ACN:454654544 Contractor Licence: 64813235
8th September, 2014
The Manager
Best Constructions Pty Ltd
52 Pearl Street,
Liverpool NSW 2170
Attention: John Smith
Dear Sir,
Re: Unit Block - 2135 The Boulevarde, Strathfield
Formwork & Concrete Tender
Further to tender documents dated 20th August 2014, we have pleasure in submitting our
firm lump sum tender for concreting and formwork to the above project, in accordance with
tender documents supplied.
All formwork as detailed to basement slabs beams columns and ramps $115,800
All reinforcement and concreting works on supply place and finish basis to basement slabs
beams columns ramps & Dincel walls to and including level 1 slab $305,400
TOTAL $421,200
Our day labour rate is $75 /hr normal hours.
We have included eight (8) setups of a concrete boom pump only, additional setups are
$750 each. We have included to supply sheds/ amenities for our own work force.
We have not included for any concrete testing, curing or hoisting, except limited pumping.
We have not included for sand blinding, 'Fortecon' slab underlay, termite control or rubbish
removal.
We assure you of our utmost cooperation in the expediting of the works. We estimate that
the works will be completed in 70 working days from possession of a clear site after
completion of bulk earthworks, sand blinding and membrane placement by others.
Yours sincerely,
Mark Power
Manager
LA018492 Assessment 4 CPCCBC5005A Ed 1 9
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014P & W Concreting Services Pty Ltd
Unit 12 / 5 Mars Road, Parramatta NSW 2124
Phone: (02) 9555 6776 Fax: (02) 9555 6777
ABN: 36776532455 Contractor licence: 9174625C
Concretors - Reinforcement Fixers - Formworkers.
No job too small or too big
Working to QUALITY MANAGEMENT SYSTEM compliant with ISO 9001
13th September, 2014
The Manager
Best Constructions Pty Ltd
52 Pearl Street,
Liverpool NSW 2170
Attention: John Smith
Dear John,
Re: Project: 2135 The Boulevarde, Strathfield
Quotation for Concrete & Formwork
We have pleasure in submitting our quotation for the following works on the above project,
as per documents enclosed in your 'invitation to tender' dated the 20th August 2014. Our
quotation is valid for 30 days, after which time we reserve the right to revise the quotation.
We have included an allowance for the following:
- Supply, place and strip class 2 suspended formwork $95/m2
- Supply and place steel reinforcements to slabs beams and walls $2,200/t
(Reo quantity based on weighbridge load calculations not delivery dockets)
- Supply, place and finish 32 MPA concrete $198/m3
(Concrete quantity to be taken from concrete truck delivery dockets)
- We have allowed for 12 only concrete pump setups, additional setups will be
charged at $480 each
- We have included termite control and sand blinding and laying only of the
membrane.
We have excluded the following Items:
- No allowance for the supply of membrane - by others.
- No allowance for curing of concrete - by others.
- No allowance for concrete testing - by others.
- No allowance for hoisting of materials or supply of workers sheds.
- No weekend work or work after 4pm.
- No removal of any rubbish generated by this trade off the site
Our day labour rate is $67.00 per hour normal time. We have estimated that the works
would be completed in 72 working days.
Should you require any additional information please contact the undersigned.
Yours faithfully
Anthony Oussa
Estimator
10 LA018492 Assessment 4 CPCCBC5005A Ed 1
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014Part 3 Manage subcontractors
In this part you need to develop a range of documents and procedures for use managing
subcontractors over the life of a building project similar to that detailed and used on the
Strathfield Apartment project.
a. Prepare a subcontractor pre award interview template that you can use when
assessing and comparing the merits and suitability of lowest tenderers. Many
companies include in their subcontracting procedure a requirement that the lowest 2
tenderers are interviewed. The template is to be used to record the interview and
determine whether the subcontractor has allowed for all work needed. It should
include adequate coverage of the following areas:
• General contract, special conditions and pricing
• Suitability (licencing, insurance, supervisors, number of workers, financial, other
projects etc.)
• Programming (working week length, start & finish dates etc.)
• Insurance (kinds, currency and policy numbers etc.)
• Code of Practice compliance
• Safety
• Quality assurance
• Ancillary, incidental and contractual items, and builders work with the trade (i.e.
crane, hoisting, storage, penetrations.)
• Schedule of facilities/services/plant and whether supplied by builder or tenderer
• Payment conditions
• Authorised parties signatures
f. Prepare a procedure (that is a brief written description of requirements) and a
template for the selection of subcontractors not currently on the company
books Make sure you include the selection criteria to be used, how to gather
information about previous work history, and requirements for qualification, licence
and credit checks.
g. Describe the communication process to be adopted and used by
subcontractors on the site i.e. printed or electronic, mail or web based, site
meetings, etc. to facilitate document distribution, access, retention, verification and
checking of communications
h. Prepare a procedure (that is a brief written description of requirements) and
templates for use in the performance management of subcontractors. You should
consider and include in the procedure the following 2 (two) aspects:
• How to deal with poor subcontractor performance. Outline steps you would
take to conduct a performance interview with a subcontractor about
unsatisfactory work quality, speed of work etc. Include key questions you would
ask, activities you would include in any action plan, and details of the monitoring
you would undertake to ensure that poor performance does not happen again.
Explain which staff you would interview to investigate the poor performance.
Provide a template for use to record a meeting about unsatisfactory performance
under the contract and record agreed solutions.
• How to evaluate and record and summarise overall subcontractor
performance on completion of the work. The procedure can state who should
evaluate performance i.e. job supervisors/site managers and the items to be
considered. Also provide a template for use to record the evaluation. Areas you
could consider in the overall performance evaluation include time, cost, quality,
environmental, WHS, personnel, industrial relations and similar parameters.
Include a place on the template to record a recommendation whether to reuse.
Will the outcome be disclosed to subcontractors?
i. Prepare an outline of items to be explained at the site induction of contractors on the
project, including any commencement forms and paperwork that would need to be
completed.
LA018492 Assessment 4 CPCCBC5005A Ed 1 11
© New South Wales Technical and Further Education Commission, 2014 (TAFE NSW – WSI), Version 1, October 2014Submit each item above to complete this part i.e. Items a, b, c, d and e.
Checklist
I have:
• answered all questions in the space provided
• clearly identified my answers
• Included my name, Student Number, Unit Number, Assessments Number.
• Reviewed and spell checked my document.
• Saved a copy of the assessments on my own computer.
12 LA018492 Assessment 4 CPCCBC5005A Ed 1