Assignment title: Information
MGMT- 404 PROJECT MANAGEMENT
STATEMENT OF PARTICIPATION
This document will contain the information needed for your team operations, guidelines and
commitment. It should be kept in doc sharing and each update should have a version control identifier
(e.g., Team A SOP v1, v2, v3, etc.).
IMPORTANT NOTE: The statement of participation must be posted in the team’s doc sharing area and
the final submission must be available for the team to review and approve each week. Approval can be
achieved by downloading the document. If you have disagreements, it is critical to contact your project
leader and get a correction posted immediately. The professor should be notified of any disagreements.
If the statement of participation is not submitted, the entire team will receive the same grade (including
any point loss from other team members).
I. TEAM INFORMATION
PROJECT NAME:
MEMBER NAME # PHONE # EMAIL MEETING AVAILABILITY
1
2
3
4
5
6
7
II. WEEKLY MEETING SCHEDULE
The most successful teams schedule at least (2) meetings a week throughout the course. Scheduling
standing meetings allows everyone to schedule this time in advance and coordinate other activities
around the scheduled meeting times. Meetings can change, based on the project leader for the week,
however, it is highly recommended that you set a meeting based on the majority team availability. In
addition to setting meetings, the most successful teams also set a deadline for drafts to be turned into
the project leader each week. Putting this structure in place early in the course will help the team to
achieve a high level of organization and success.
MEETING DAY TIME
Review weekly assignment
Deadline for weekly drafts
Review Draft
III. PROJECT DESCRIPTION
Brief synopsis of your proposed project in 200 words or less. Describe the overall project with enough
information to gain approval for your team to use this project as the course project. If you are working
on a project in the instructions, you do not need to gain approval. Approval is only needed if you select a
project outside of the list in the course project instructions.
IV. TEAM MANAGEMENT PLAN
a. Team Leadership: Designate the project leader for each major deliverable. Project leader can be
rotated so that each team member experiences the leadership responsibilities or you can establish one
primary project leader with a back-up to assist. The project leader has specific responsibilities each week
as follows:
a. Schedule the weekly meetings as directed by your Professor, facilitate and record the meetings.
b. Set the deadlines for submissions each week.
c. Compile the team submissions into one document and submit to the dropbox. “ONLY ONE”
submission is required and this is submitted by the project leader.
d. Update the statement of participation status each week and submit to dropbox for the team
review.
e. Place the final submission and updated statement of participation in the team’s doc sharing area
each week.
f. Contact the professor with any team questions, issues, or conflicts.
Weekly Deliverable Due Weekly Project Leader Assignment
Statement of Participation Week 1
Project Charter Week 2
Project Scope Statement Week 3
WBS and Network Diagram Week 4
Risk Management Plan Week 5
Resource Management Plan Week 6
Communications Plan Week 7
Final Project Week 8
b. Task assignments: How will tasks be assigned? Every team member should have an active role in
creating the tasks for each major deliverable. All (8) weeks of assignments must be completed.
Week 1: Statement of Participation Team Member Responsible
• Team Information Each team member submit to project leader
• Project Leadership Each team member submit to project leader
• Task Assignments Weeks 1-8 (Each project leader can assign the task for their week or team
members can select what they want to work on each week). Project leader for Week 1
• Commitment statement Each team member submit to project leader
• Weekly Status Update Project leader for Week 1 update the status update at the end of the
SoP document and submit to dropbox and place copy in doc sharing for team review.
Week 2: Project Charter Team Member Responsible
• Mission/Project Purpose
• Project Description, Product and deliverables
• Objectives
• Business Need
• Milestones
• Budget
• User Acceptance Criteria
• Project Assumptions
• Project Constraints
• Exclusions and Boundaries
• Major Risks
• Project Stakeholders
• Weekly Status Update Project leader for Week 2 (submit final assignment and SoP to dropbox
and place copy in doc sharing for team review)
Week 3: Scope Statement Team Member Responsible
• SOW and Project Product
• Project Deliverables
• Project Objectives
• Project Assumptions
• Project Constraints
• Exclusions
• Acceptance Criteria (includes table format for quality signoff).
• Technical Requirements
• Weekly Status Update Project leader for Week 3 (submit final assignment and SoP to dropbox
and place copy in doc sharing for team review)
Week 4: WBS / Project Schedule Team Member Responsible
The best approach to divide the work task and assign each team member a section or responsibility
(e.g., Planning phase, Purchasing Phase, etc.). Then assign someone to setup durations, dates and
predecessors. Resources can be defined on the resource sheet, but remember…no resources are
assigned to the project tasks at this point.
• Project Schedule WBS (task definitions, durations, dates, predecessors, etc.)
• Weekly Status Update Project leader for Week 4 (submit final assignment and SoP to dropbox
and place copy in doc sharing for team review)
Week 5: Risk Management Plan Team Member Responsible
The best approach to divide the work is to assign each team member a specific number of risk, for
example John has negative risk 1-5, Jane has negative risk 6-10. This information is needed in order to
assess each “individuals” contribution.
• Risk Register
• Weekly Status Update Project leader for Week 5 (submit final assignment and SoP to dropbox
and place copy in doc sharing for team review)
Week 6: Resource Management Plan Team Member Responsible
• Assign resources and costs to the project with any materials, equipment or fixed cost
allocations.
• Project Budget Report
• Resource management report
• Weekly Status Update Project leader for Week 6 (submit final assignment and SoP to dropbox
and place copy in doc sharing for team review)
Week 7: Communications Plan Team Member Responsible
This is a short assignment because of the quiz. There is no division necessary, however each team
member must provide input to the person responsible for completing the form. The best approach is to
have a team meeting and discuss completing the template. All team members must attend the meeting
and provide input to receive credit for this section. The project leader for this week should complete the
template and submit it to the dropbox.
• Communications Plan Template
• Weekly Status Update Project leader for Week 7 (submit final assignment and SoP to dropbox
and place copy in doc sharing for team review)
Week 8: Final Project Package Team Member Responsible
• Executive Summary (Overview of the project and current updates in 2-3 pages)
• Project Charter
• Scope Statement
• Work Breakdown Structure
• Risk Management Plan
• Project Schedule and Budget (.mpp file)
• Communications Management Plan
• Weekly Status Update Project leader for Week 8 (submit final assignment and SoP to dropbox
and place copy in doc sharing for team review)
NOTE FOR WEEK 8: If the assigned person places the updated component in the template each week
after grades are complete, you will be building the final project. If everything works out with the
updates, the only thing to do in week 8 review the contents, format the document for consistency and
professionalism and you’ll be ready for submission.
V. TIPS FOR CONFLICT MANAGEMENT RECOMMENDATIONS
a. Think about potential barriers and coping strategies such as barriers to the achievement of the
assigned goals, e.g. time zone, time management, language skills, and identify coping strategies.
b. Discuss your team operational GROUND RULES: (include meeting schedule, attendance
expectations, agenda, and communication methods.):
c. Consider how will you manage conflict? Consider how team members quickly identify conflicts
to address them for resolution.
d. Plan for minor disagreements, inability to agree on submissions? It’s ok to agree to disagree!
e. Consider who will have final say for major disagreements? Majority rule or leader?
f. Discuss the method of communicating with team members who do not deliver?
g. Remember, every team member may not receive the same grade.
h. If you feel a situation is going to get out of control, contact the professor early so that
appropriate actions can be taken.
VI. Commitment
Each team member is to write an individual commitment statement indicating your responsibility to the
team for your participating, meeting attendance and completing the assigned deliverables. (if on-site,
each team member will sign their commitment statement).
Team Member Statement of Commitment
WEEKLY PARTICIPATION STATEMENT
Remember, the weekly participation statement will serve as input to your individual grades. Your
participation statement is a short narrative status report which indicates how the project went for the
week, who did what on the project deliverables and any additional comments, issues or concerns for the
week.
ENTRY EXAMPLE: Each person on the team completed their assigned work this week. Mary, Joe and Nick
attended all meetings, posted to the team meeting area and completed their assigned sections on time.
John was late with submitting his draft and did not attend any meetings. Paul was not able to attend
meetings due to work commitments, however he completed all assigned work and submitted it on time.
The team is having problems with overall XYZ and would like the professor’s direction on how to resolve
these issues.
Week Participation Status Report
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
IMPORTANT NOTE: The statement of participation must be posted in the team’s doc sharing area and
the final submission must be available for the team to review and approve each week.