Assignment title: Information
Assessment Item 2 – Group Case Study
Due Dates: See Moodle for the exact date and time for the submissions listed below:
Individual student sub-deliverable submissions:
Sub-deliverable 1: End of week 6
Sub-deliverable 2: End of week 7 (plus peer assessment)
Sub-deliverable 3: End of week 8 (plus peer assessment)
Sub-deliverable 4: End of week 9 (plus peer assessment)
Sub-deliverable 5: End of week 10 (plus peer assessment)
Final Group submission: End of week 11 (35 marks)
Weighting/Total: 40%
Important notes regarding assignment submissions:
1. Individual student sub-deliverable submissions are to be submitted by all members of the
group as zip files in their own submission area on the Moodle unit website. These are your
individual attempts at the work before your group meeting. Each individual submission has a
different due date. Exact dates and times are given on the Moodle unit website. The table
below provides a summary of what is to be submitted in the zip files for each individual
submission.
Sub-deliverable Week
due
Description of zip file contents
1 6 A zip file with your .mpp files saved at the end of practicals 1, 2 and 3.
2 7 A zip file containing the Part A question 1 .mpp file, i.e. PartAQ1.mpp and
your completed peer assessment form(s)
3 8 A zip file containing:
1. Word document with answers for Part A
2. PartAQ2.mpp
3. PartAQ3_resources.mpp
and your completed peer assessment form(s)
4 9 A zip file containing
1. A Word document with the answers to Part B
2. PartB.mpp
and your completed peer assessment form(s)
5 10 A zip file containing:
1. A Word document with your answers to Part C questions
2. A copy of your group’s PartC.mpp
and your completed peer assessment form(s)
2017Page | 1
Note: individual submissions are not marked in detail. Markers will check your work to ensure that
you have an on-time submission and that you have prepared your answers in readiness for your group
meeting. All marks for this assessment item depend on students making a satisfactory contribution to
the group. If students are not contributing they may be asked to work on the assignment as an
individual and/or have marks adjusted. Both peer assessment and individual submissions will be taken
into account.
Markers may provide some comments and/or ask you to meet with them during your tutorial/practical
class.
2. Late submissions of individual sub-deliverables will automatically be given a mark of 0.
Individual sub-deliverables must be submitted on-time with peer assessment to be awarded
marks.
3. You must aim to submit your assignment and individual sub-deliverable submissions at least
1 hour before the due date. This will avoid unnecessary late penalties if you have any
technical issues while submitting your assignment.
4. If you do experience a problem uploading your assignment online and cannot get help from
TASAC, make sure that you email your assignment files to your tutor before the due date.
This will allow your tutor to view the work that was completed before the deadline. Note
that you will also be required to submit the assignment online through Moodle as soon as
possible.
5. Currently, any drafts in Moodle are automatically submitted by Moodle on the due date.
However, you should not rely on this for your submission as this default behaviour may
change. This also means that you should not leave something uploaded as a draft if you do
not want to it to be submitted automatically on the due date.
6. If you upload after the due date (even with an extension) you must ensure that you press
submit for marking when you upload your work.
7. All group members are responsible for checking that the correct versions of the files
for the final group submission are submitted on time. The answers in the Word
document must correspond to the data in the mpp files.
Additional Notes:
1. You are required to take your current versions of your Microsoft Project practicals and
assignment 2 to your tutorial/practical classes from week 3 onwards. You are scheduled to
commence the Microsoft Project practicals in week 3.
2. Remember that it is your responsibility to keep backups of all your work and of
your current version of the final group assignment.Page | 2
Contents
Overview .................................................................................................................................................3
The Case study ........................................................................................................................................4
Background .........................................................................................................................................4
Initial Data...........................................................................................................................................4
Assessment Tasks..................................................................................................................................11
Assumptions......................................................................................................................................11
Part A: Developing the Schedule ......................................................................................................11
Part B: Modifying the schedule.........................................................................................................14
Part C: Tracking Progress ..................................................................................................................15
Saving the baseline and entering the status data (together as a group)......................................16
Status Report ................................................................................................................................17
Assessment Submissions.......................................................................................................................18
Individual submission of sub-deliverables........................................................................................18
Peer Assessment...............................................................................................................................19
Final Group Submission ....................................................................................................................19
Content of the Word Document in the final submission..................................................................20
Marking Guide/Criteria .........................................................................................................................21
Appendix 1: Status Report Template....................................................................................................22Page | 3
Overview
This case study simulates a project management scenario where the student takes on the role of
project manager. Students are required to use Microsoft project management software as part of
this assessment task.
This is a group assignment that also includes five individual student submissions (see below). You
should aim for groups of four students. Four is the maximum number of students allowed in a
group. Ideally, no group should have fewer than 3 students. (Note that distance education students
have the option of smaller groups or working on this as an individual assignment. To form groups
with other distance education students, use the distance education forum on the unit website.)
Although this is a group assignment, all members of a group are required to attempt all parts of the
assignment individually as assessment item sub-deliverables 1- 5. Members of the group are
required to submit their own individual attempt for each of the sub-deliverables in Moodle before
the group meets to consolidate answers to produce the "group solution". There are separate
submission areas and due dates for the individual submissions. On time submission of the 5 subdeliverables is worth a total of 5 marks, but these submissions are also be used to assess individual
contributions and may impact on a student’s final mark. Late sub-deliverable submissions will be
given a mark of 0.
Groups must meet at least once a week to produce the “group solution” for the most recently
submitted individual sub-deliverable. This solution should then be added to the “in progress” final
group solution. All members of the group must keep a copy of the “current group assignment”.
It is also important to meet early in week 10 to produce the updated schedule to be used to
complete the Part C questions and status report. Each group is responsible for providing their own
status data. This means that the group members must collaborate to produce the PartC.mpp file to
be used to complete the Part C questions. This is explained further in part C.
There is one final group solution to be submitted at the end of the assignment. It is worth 35 marks
and is to be submitted by only one member of the group. The names and student ids of all members
of the group must appear clearly on the coversheet of the final assessment submission.
Peer assessment and your individual submissions will also be used to assess group member
contributions. If any member of a team is not contributing satisfactorily to the group then he/she
may have marks adjusted and/or be asked to leave the group and be required to complete the
assignment as an individual. If you are having any difficulties within your group you must alert
your tutor/lecturer as early as possible.
To assist students in their assessment solution development the following information is provided:
1. A product development case description.
2. Specific assessment questions that must be answered.
3. Information regarding the submission of the assessment.
4. Marking criteria.
Where necessary, students are expected to find relevant information in the academic literature to
justify their answers. Any assumptions made must be clearly documented.Page | 4
The Case study
Background
Xyzzy is a corporation that was formed to merge three different financial institutions. Each of the
three financial institutions involved in the merger already had systems that complied with legislative
requirements and had systems that allowed investors to monitor their investments and engage in
regular trading. However, each of the original institutions had their own internal processes, financial
systems, programming standards, databases etc. The new corporation is quite large, and given its
size, it is not surprising that there are a diverse range of investors. Some of the investors hardly ever
bother checking on their investments, while others monitor them regularly and engage in regular
trading.
The Chief Executive of Xyzzy recognised that the future of the new corporation depended very much
on the development of a new financial system to be used throughout Xyzzy. Given the importance of
the new system, a project manager (David Grey) was appointed to manage the project. David had
extensive project management experience and had successfully managed a number of similar
projects.
Initial Data
After one week, David finalised a draft organisation chart. This showed that there would be a need
for staff from several specialist areas. He arranged a meeting with the Human Resources Manager
(Michael Brown) to proceed with appointments of “section leaders” for each specialist area. Michael
agreed with the chart and arranged for someone from HR to help David with the development of
position descriptions for the staff required.
The positions are to be advertised internally for three weeks. Another 2 weeks are to be allowed for
interview processes and 2 weeks for the staff to be released from their current positions before they
can commence on the project (i.e. a total of 7 weeks to appoint “section leaders”).
The following table shows the specialist areas and number of staff in each area (including the section
leaders).
Section Number of Section
Staff (including the
section leaders)
$/hour
Operations (OP) 2 $80
Analysts (AN) 3 $95
Database (DB) 2 $90
Software Engineers (SE) 3 $90
Telecommunications (TC) 1 $85
Security(SEC) 1 $90
Conversion Team (CT) 3 $60
Table 1: Specialist Areas (Sections)Page | 5
Note:
• Although there will be “section leaders”, assume that all staff members in a section have
the same salary and can be assigned to any of the tasks requiring expertise from their area.
• In the table above abbreviations are given for each section resource. For example, a
software engineer is abbreviated to SE.
• Assume that (apart from holidays) the staff work a 40 hour week from Monday to Friday
(i.e. a 5 day week with 8 hour days). This means that in table 2 below one week equates to 5
days (Mon-Fri).
Assume that David will meet with the section leaders on their first day to explain the importance of
the new system and to provide them with the preliminary details of the project. They will be
required to provide any modifications within 1 week of that initial meeting. Assume that at the end
of the week David has the information provided in the following table:
Task Name Description Predecessor(s) Resource
and
Duration
Estimates
To be completed
before the
milestone
Xyzzy Financial System
1 Recruitment
1.1 Recruitment of
section leaders
This is to be the start of
David’s schedule. It
assumes that the
charter has been signed,
David has developed the
organisation chart and
the position descriptions
for Section leaders have
been developed.
start of project
schedule
(Milestone 1 –
M1) (start date:
5th June 2017)
7 weeks.
Note that no
resources
are allocated
to this task
although HR
staff and the
PM will be
involved in
this task.
1.2 Appointment of other
section staff
1.1 2 weeks.
Note that no
resources
are allocated
to this task
although HR
staff, section
leaders and
the PM will
be involved
in this task.
2 Development of
Common Standards
2.1 Database Standards This will involve
consultation with other
members of the team
and IT staff from the
three initial
corporations.
1.2 2 personweeks of DBPage | 6
2.2 Programming
Standards
This will involve
consultation with other
members of the team
and IT staff from the
three initial
corporations.
1.2 2 personweeks of SE
3 Telecommunications
3.1 Analysis of existing
contracts and
requirements
1.1 2 personweeks of TC
3.2 Negotiation of new
contracts
3.1 4 personweeks of TC
3.3 Delivery time 3.2 2 weeks
(fixed
duration)
3.4 Installation and
testing
3.3 1 personweek of TC
4 Security
4.1 Review of existing
security
1.1 3 personweeks of SEC
4.2 Develop security
requirements document
4.1 4 personweeks of SEC
4.3 Security development 4.2 4 personweeks of SEC
5 New hardware
5.1 Preparation of
quotation
6.1 4 personweeks of OP
5.2 Period quotation
open
5.1 4 weeks –
fixed
duration
5.3 Acceptance of
quotation
5.2 2 personweeks of OP
5.4 Lead time for delivery 5.3 4 weeks –
fixed
duration
5.5 Installation 5.4 1 personweek of OP,
1 person
week of SE, 1
person-week
of SEC
(ideally the 3
staff working
together on
installation
matters for 1
week)
6 Software
6.1 Detailed
Requirements Analysis
1.2 12 personweeks of AN
M2Page | 7
6.2 Database extraction
program for corporation
1
6.2.1 Design of DB
extraction program for
corporation 1
2.1,2.2,6.1,6.11.1 3 personweeks of SE
6.2.2 Coding of DB
extraction program for
corporation 1
6.2.1 6 personweeks of SE
6.2.3 Testing of DB
extraction program for
corporation 1
6.2.2 2 personweeks of SE
M3
6.3 Database extraction
program for corporation
2
6.3.1 Design of DB
extraction program for
corporation 2
2.1,2.2,6.1,6.11.1 3 personweeks of SE
6.3.2 Coding of DB
extraction program for
corporation 2
6.3.1 6 personweeks of SE
6.3.3 Testing of DB
extraction program for
corporation 2
6.3.2 2 personweeks of SE
M3
6.4 Database extraction
program for corporation
3
6.4.1 Design of DB
extraction program for
corporation 3
2.1,2.2,6.1,6.11.1 3 personweeks of SE
6.4.2 Coding of DB
extraction program for
corporation 3
6.4.1 6 personweeks of SE
6.4.3 Testing of DB
extraction program for
corporation 3
6.4.2 2 personweeks of SE
M3
6.5 Database Upload
program for new DB
6.5.1 Design Upload
program for new DB
2.1,2.2,6.1, 6.11.1 2 personweeks of SE
6.5.2 Code Database
Upload program for new
DB
6.5.1 4 personweeks of SE
6.5.3 Test Database
Upload program for new
DB
6.5.2 2 personweeks of SE
M3
6.6 Daily update share
and unit prices
6.6.1 Design Daily update
share and unit prices
2.1,2.2,6.1 1 personweek of SEPage | 8
6.6.2 Code Daily update
share and unit prices
6.6.1 2 person-
2eeks of SE
6.6.3 Test Daily update
share and unit prices
6.6.2 1 personweek of SE
M3
6.7 Investor portfolio
reports
6.7.1 Design Investor
portfolio reports
2.1,2.2,6.1 1 personweek of SE
6.7.2 Code Investor
portfolio reports
6.7.1 2 person-
2eeks of SE
6.7.3 Test Investor
portfolio reports
6.7.2 1 personweek of SE
M3
6.8 Unit prices history
report
6.8.1 Design Unit prices
history report
2.1,2.2,6.1 3 persondays of SE
6.8.2 Code Unit prices
history report
6.8.1 1 personweek of SE
6.8.3 Test Unit prices
history report
6.8.2 3 persondays of SE
M3
6.9 Margin loan
simulation program
6.9.1 Design Margin loan
simulation program
2.1,2.2,6.1 2 personweeks of SE
6.9.2 Code Margin loan
simulation program
6.9.1 3 person
weeks of SE
6.9.3 Test Margin loan
simulation program
6.9.2 1 personweek of SE
M3
6.10 Investor personal
Details Maintenance
6.10.1 Design Investor
personal Details
Maintenance
2.1,2.2,6.1 1 personweek of SE
6.10.2 Code Investor
personal Details
Maintenance
6.10.1 2 personweeks of SE
6.10.3 Test Investor
personal Details
Maintenance
6.10.2 1 personweek f SE
M3
6.11 Database
6.11.1 Design New
Database
2.1,2.2,6.1 4 personweeks of DB
6.11.2 Develop New
Database
6.11.1 4 personweeks of DB
6.11.3 Test New Database 6.11.2 2 personweeks of DB
M3
6.12 Integration and
Testing
3.4, 4.3, 5.5, all
software testing
tasks completed
(i.e. 6.2.3, 6.3.3,
2 personweeks of SE,
2 personweeks of
SEC, 2
M4Page | 9
6.4.3 …. 6.11.3 or
M3)
personweeks of DB
(assume all
three staff
are working
together
over the 2
weeks)
7 Conversion Note that this must not
to be carried out
simultaneously at each
corporation. There is to
be a 2 month delay
between conversions.
7.1 first conversion (of first corporation) 6.12 2 days fixed
duration
with all
members of
the
“conversion
team”
working on
this together
(i.e. 6
person-days)
7.2 second conversion (of second corporation) 8 weeks after 7.1
is complete
2 days fixed
duration
with all
members of
the
“conversion
team”
working on
this together
7.3 third conversion (of third corporation) 8 weeks after
second
conversion (7.2) is
complete
2 days fixed
duration
with all
members of
the
“conversion
team”
working on
this together
8 Training
8.1 corporation one 7.1 4 weeks
fixed
duration.
Two CT staff
to be
assigned to
this taskPage | 10
together (8
personweeks).
8.2 corporation 2 7.2,8.1 4 weeks
fixed
duration.
Two CT staff
to be
assigned to
this task.
8.3 corporation 3 7.3,8.2 4 weeks
fixed
duration.
Two CT staff
to be
assigned to
this task.
M5
Table 2: Work Breakdown structure, Predecessor and Resource Requirements
The milestones for the project are:
1. M1: The start of the project
2. M2: Detailed Analysis complete
3. M3: All software programs complete (including individual testing)
4. M4: Integration and testing complete
5. M5: All the deliverables, conversion and training completePage | 11
Assessment Tasks
Assumptions
You are free to make any assumptions necessary to complete the assignment. However each
assumption must be justified and stated clearly in your assessment word document. Marks will be
deducted for any unreasonable assumption or for stating an assumption and then ignoring it in your
assignment.
Part A: Developing the Schedule
For part A of the assessment you must complete the following tasks and questions. Read all the
questions before you commence the tasks. The schedule is to be developed in an appropriately
named Microsoft Project 2013 file (see the name specified below) and the questions are to be
answered in a Word document. Any assumptions must also be listed at the beginning of the Word
document (after the coversheet).
1. Use Microsoft Project to develop the project schedule according to the instructions below.
For this assignment, unless the specification states otherwise, you must initially allocate only
one of each required resource to a task. To clarify, some examples are given below. For
example, based on the information in table 2, you should initially allocate:
• One Analyst to work on task “6.1 Detailed Requirements Analysis” for 12 weeks.
• One Operations staff member, one Security specialist and one Software Engineer to
work together on task “5.5 Installation of the new hardware” for 1 week.
• All three of the conversion team to work together on each of the conversion tasks
(7.1-7.3). With this “team”, each conversion task should have a duration of 2 days.
• Two members of the conversion team to work together on each of the training tasks
(8.1-8.3). With this “team”, each training task should have a duration of 4 weeks.
All tasks must be automatically scheduled tasks for this assignment. Remember to make
this the default setting before you begin adding tasks to your schedule.
David is required to report directly to Ms. Thurlings in the PM Office. Ms. Thurlings has
asked that the following be included in the schedule:
i. The following holiday/non-working times:
A general holiday period between 25/12/17 to 2/01/18
Public holiday on 26/1/18.
ii. A project title of “Xyzzy Finance System”. This is also to appear as the overall
project summary at the top of your “WBS” in the mpp file. It must appear as task 0
with WBS number 0. All tasks should be “indented” according to the WBS structure
described in the case study (see table 2). See the Microsoft Project practicals for
details about how to add the project title and how tomake it the overall project
summary.
iii. A WBS column before the “Task Name” column and a WBS Predecessors column
after the “Task Name” column as shown below:Page | 12
(task
number
– no
column
title)
Task
Mode
WBS Task
Name
WBS
Predecessors
Duration Start Finish Predecessors Resource
Names
iv. The milestones are to appear at the end of the task list in your schedule. See the notes
after table 2 for more details about the project milestones. (Note that this is not
always a requirement in a project schedule. Milestones can be embedded in the
schedule or listed at the start. In this assignment you are required to add them at the
end.).
v. Ms. Thurlings has also asked you to use a “customised WBS code” for the
milestones. For example, if you double click on the first milestone, you can change
the WBS code to M1 as illustrated in the screenshot below.
vi. Resource allocation details.
vii. The critical path(s) automatically displayed in red on the bars of the Gantt chart view
of your schedule
At this point there may be resource over allocation issues. Do not attempt to resolve these
before answering question 2. Save this version of your schedule in PartAQ1.mpp. You will
be required to submit this file as part of your assignment submission.
2. At this point ignore any resource over allocations. Copy your PartAQ1.mpp schedule to
PartAQ2.mpp:
i. Ms. Thurlings asks you to allocate all three analysts to task “6.1 Detailed
Requirements Analysis”. Assume that with the additional resources the task stillPage | 13
requires “12 person-weeks” (i.e. that there will be a reduction in duration as the work
can be divided equally among the three resources).
a) What is the new duration of task 6.1 and has this change impacted on the
overall duration of the project? Explain.
b) Does adding resources to a task always reduce the duration in this way?
Explain your answer. (Hint: your explanation should include some
discussion of the “mythical man month”.)
ii. Save PartAQ2.mpp. You will be required to submit this file as part of your
assignment submission.
3. Copy your PartAQ2.mpp schedule to PartAQ3_resources.mpp. If your schedule has any
resource over-allocation issues resolve these in the PartAQ3_resources.mpp file without
adding any additional resources. For this assignment, do not “split tasks” and do not
allow levelling to “adjust individual assignments on a task”.
Save this “modified” version of the PartAQ3_resources.mpp file. You will be required to
submit the PartAQ3_resources.mpp file as part of your assignment submission.
i. Describe how you used (or how you would have used Microsoft Project) to resolve
any resource over-allocation issues.
ii. Does the fact that you cannot add any additional resources to resolve resource overallocation for this project have any impact on your overall project duration and end
date? Explain why/why not.
Continue working with this version of the schedule (PartAQ3_resources.mpp) when you are
answering the remainder of the questions in Part A.
4. Write a memo to Ms. Thurlings providing the following information:
i. the expected completion date of the project, assuming it commences with task 1.1 on
5th June 2017;
ii. the total duration of the project;
iii. an explanation of the main factors that cause the project to require that length of time
and any recommendations that you might make to reduce the duration if time was a
priority for the project;
iv. the estimated direct labour costs for each of the resource types working on the
project. Present the costs in a table similar to the following:
Resource Name Cost
Operations
Software Engineers
Analysts
Security Specialists
Database Specialists
Conversion Team
Total direct labour costs:
Assume that you will send the project schedule as an attachment to the memo. The
information in the memo must correspond to the PartAQ3_reoources.mpp file.Page | 14
Information about writing memos can be found on the unit website in the same area
as this specification.
5. Are there any tasks/activities or deliverables that you believe may have been overlooked and
should be included in your WBS? You should be able to identify at least one possibility.
Part B: Modifying the schedule
You are required to make the following changes to the estimates for Tasks 6.11.1-6.11.3 (New
database tasks) and 4.3 (security development):
Task New Resource and Duration
Estimates
6.11.1 8 person-weeks of DB
6.11.2 8 person-weeks of DB
6.11.3 4 person-weeks of DB
4.3 6 person-weeks of SEC
In addition, Ms. Thurlings has asked you to:
• assign both Database specialists to work together on tasks 6.11.1-6.11.3;
• reduce the time between conversion tasks from 8 weeks to 6 weeks.
Based on the information given above complete the following tasks. Read all the tasks before you
commence.
1. Copy your PartAQ3_resources.mpp file into a file called PartB.mpp file..
In your PartB.mpp make the changes in the order given in the tables below and as you
make each change note the impact it has on the:
• overall project duration
• end date
• direct labour costs for the project
relative to the “current status” (i.e. the status after the previous change).
You need the information about the impact of each change to answer questions 2 and 3 below.
If as a result of all the changes there are any resource over-allocation issues resolve these and
note any resultant change to the project duration.
Highlight all the changes on your schedule. Save your schedule with the highlighted
changes in your PartB.mpp file. This PartB.mpp file is also to be included as part of your
final assignment submission.Page | 15
2. Describe the impact of each of these changes on the project duration in a table similar to the
following:
Change Impact on project duration
(longer, shorter or no
impact)
By how much Explanation
Change in person-weeks required for tasks
6.11.1-6.11.3
Allocation of both DB specialists to tasks
6.11.1-6.11.3
Change in person-weeks required for task 4.3
Reduction in time between conversion tasks
If the combination of changes have had an additional impact that would not have occurred if a
change was made in isolation you should also discuss this in your answer to this question.
Similarly, if there were resource over-allocation issues that had to be resolved and resulted in
a change to the duration, this should also be discussed.
3. Describe the impact of each of these changes on the direct labour costs for the project in a
table similar to the following:
Change Impact on direct
labour costs
(more, less or no
impact)
By how much Explanation
Change in person-weeks required for tasks
6.11.1-6.11.3
Allocation of both DB specialists to tasks
6.11.1-6.11.3
Change in person-weeks required for task 4.3
Reduction in time between conversion tasks
Part C: Tracking Progress
In this part of the assignment you are to imagine that your project is underway and that it is time to
produce one of your regular status reports.
This means that your group needs to meet together early in week 10 to save the baseline and enter the
status data for your project. Your group must enter the data together and make sure that everyone
has a copy of the updated PartC mpp file. This is to ensure that everyone in the group is working with
the same information when they develop their individual status report.
The individual sub-deliverable due at the end of week 10 includes the group’s version of the
PartC.mpp file plus your individual answers to the Part C questions.
In week 11, you must meet to complete the group version of the Part C answers and include this in
your final group submission. All previous “group” answers should already have been completed
before week 11.Page | 16
Saving the baseline and entering the status data (together as a group)
Note that the fourth Microsoft Project practical is an example of what is required for Part C. Make
sure that you have worked through practical 4 before attempting Part C of this assignment.
1. Copy PartB.mpp to PartC.mpp. Save the baseline for this version of your project in
PartC.mpp.
2. Assume that it is now 8th September 2017 and that you have data about when tasks actually
started, their duration (which must be consistent with the start date and the status date, i.e.
they cannot have a start date and a duration that takes them beyond the 8/9/17). Assume that
you have also collected data about the estimated remaining duration for all the tasks that have
commenced (but not yet finished). If a task has been 100% completed assume that you know
the actual start date and actual finish date.
Assume that status reports are produced every two weeks and that all the earlier status reports
have been completed according to this fortnightly schedule. Given that 8/9/17 is the end of
week 14, you should record the status report number as “7” when you complete the status
report for this section of the assignment.
In your PartC.mpp file (in which you have saved a baseline)
a) Set the status date to the 8th September 2017 and include a solid, purple status date
gridline in your project to ensure that the status date is clearly visible in your Gantt
Charts. View the Tracking Gantt chart.
b) Enter some status data.
• Assume that tasks 1.1 and 1.2 are 100% complete and that they started and
finished at the times scheduled in the baseline.
• For the purposes of this assignment you are to invent your own data about the
status of the other project tasks. This means that you have to enter status data
about the other tasks that you would expect to have started by the status date.
(Use the status date gridline you created in part (a) to identify tasks that
require status information.)
For tasks that should have been started by the status date you are to enter
reasonable data about their start date, actual duration (up to the status date)
and estimated duration remaining (or completion date). Do not have all tasks
starting and finishing exactly according to your original estimates and
make sure that your changes do not violate any predecessor constraints
(i.e. do not start a task before the predecessors have been completed). Aim to
enter data so that you can see a cost and/or schedule variance that you can
then interpret and explain in your status report.
You are free to enter data to make tasks finish early or late or enter data about
the remaining duration that means a task is expected to take either more or
less time than originally estimated. It is also acceptable to have some tasks
that are tracking according to their original duration estimates, but not all
tasks.Page | 17
Save your changes in PartC.mpp and use this file to answer parts c, d and e
below.
Status Report
Based on your group PartC.mpp file each member of the group must complete and submit their
individual attempts at the following tasks before meeting to produce the final group solution.
c) Add additional columns to show the CPI and SPI in the earned value table of your
PartC.mpp file. Include a screenshot of the top of the earned value table of your
PartC.mpp file in the Part C section of your Word document.
For example, if asked to do this for the Microsoft Project practical 4 schedule, you
would produce a screenshot similar to the following:
d) Based on the current status of your project, you are to produce a status report using
the template provided in Appendix 1 of this document. (It is a similar format to
“exhibit 13.1” in the textbook). Make sure that you complete all sections of the status
report.
Detailed explanations for why tasks are not tracking according to their original
estimates are not required for this assignment as the data you entered is “fictitious”.
However, in this section you must indicate which tasks are responsible for your
project status being better or worse than planned.
For the “major changes or issues” and the “risk watch” sections enter “no change”.Page | 18
Assessment Submissions
This assignment requires 5 individual submissions of the sub-deliverables online by all members of
the group and one final group submission of the complete assignment by one member of the group
only plus peer group assessments.
The individual sub-deliverables are to be submitted in weeks 6, 7, 8, 9 and 10.
The final group submission is due in week 11.
The exact due dates and times are given on the Moodle unit website. The details of what is to be
submitted for each sub-deliverable and for the final group submission are given below.
Individual submission of sub-deliverables
These are to be submitted by all members of the group as zip files in their own submission area on the
Moodle unit website. Each individual submission has a different due date. Exact dates and times are
given on the Moodle unit website. The table below provides a summary of what is to be submitted in
the zip files.
Sub-deliverable Week
due
Description of zip file contents
1 6 A zip file with your .mpp files saved at the end of practicals 1, 2
and 3.
2 7 A zip file containing the Part A question 1 .mpp file, i.e.
PartAQ1.mpp and your completed peer assessment form(s)
3 8 A zip file containing:
4. Word document with answers for Part A
5. PartAQ2.mpp
6. PartAQ3_resources.mpp
and your completed peer assessment form(s)
4 9 A zip file containing
1. A Word document with the answers to Part B
2. PartB.mpp
and your completed peer assessment form(s)
5 10 A zip file containing:
3. A Word document with your answers to Part C questions
4. A copy of your group’s PartC.mpp
and your completed peer assessment form(s)
Note that individual submissions are not marked in detail. Markers will check your work to ensure
that you have an on-time submission and that you have prepared your answers in readiness for your
group meeting. Markers may provide some comments and/or ask you to meet with them during your
tutorial/practical class.
Late submissions of individual sub-deliverables will automatically be given a mark of 0.
Make sure that you take your current version of the assignment to your tutorial class in case your
tutor wishes to provide you with feedback in the class. You (and your group) can also ask for advice
about the assignment during the class.Page | 19
Peer Assessment
The aims of this peer assessment are twofold:
1. to provide information to the markers to help with their assessment of student work
2. to give students feedback to help to improve their skills when working as part of a team.
With regard to point 1, although there are regular peer assessments scheduled as part of this
assessment item (weeks 7 -10), it is also important that you alert your tutor as early as possible if
you are experiencing problems within your group (for example, if a team member is not attending
meetings or is coming to meetings unprepared). If there are problems, it is your responsibility to
contact your tutor and discuss any issues as early as possible.
In terms of point 2, it is important that the feedback be used in a positive way. It should only include
“constructive criticism”, i.e. it should:
• Provide positive feedback so that the team member understands what they are doing that
works well.
• Provide constructive criticism, i.e. advice about how a team member could improve their
team work.
• Be polite and positive.
The Peer Assessment Forms are available on the unit website in the same area as this assignment
specification.
Final Group Submission
The final group solution with the mpp files and assignment answers must be submitted in the
electronic submission system on Moodle by one member of the group. It is important that only one
member of the group submits the work or Turnitin will produce a very high similarity score for your
work.
The final group submission is due at the end of week 11 (exact date and time shown in Moodle).
Unlike the individual sub-deliverable submissions, this submission area will not accept zip files. The
final group submission is to consist of six individual files as follows:
1. A Word document with the coversheet/title page (shown below) and the group answers to all
the questions in Part A, Part B and Part C.
2. The following group .mpp files:
a. PartAQ1.mpp
b. PartAQ2.mpp
c. PartAQ3_resources.mpp
d. PartB.mpp
e. PartC.mppPage | 20
Content of the Word Document in the final submission
To avoid problems with Turnitin, do not copy the questions from this assignment specification into
your Word document.
However, do make it as easy as possible for your marker to identify the question you are answering by
labelling each question clearly. For example:
Part A
Question 1
Your answer
Question 2
Your answer
The Word document must have a coversheet/title page at the start of the document that clearly shows
all members of the group. A template for the coversheet/title page follows.
PPMP20007
Assessment Item 2 Coversheet
Group Members:
Student Name: Student Id:
Student Name: Student Id:
Student Name: Student Id:
Student Name: Student Id:
Remember that it is your responsibility to keep backups of your work and of your current
version of the final group assignment.
Although there is to be only one submission of the final group assignment by one member of
a group, it is the responsibility of all members of the group to make sure that the correct files
are submitted by the due date.Page | 21
Marking Guide/Criteria
Assignment
Question
Criteria Marks
available
Marks
awarded
Individual Subdeliverables
Marked separately on Moodle
Part A
Assumptions Listed, justified and stated clearly at the start of the Word
document (if any )
Q1 The adequacy of the Project Schedule 7
Q2 a) Impact on duration; b) Discussion of relationship 3
Q3 Dealing with resource issues 3
Q4 Appropriateness of the written memo with all the information
included and data corresponding to the schedule.
4
Q5 Any additional tasks overlooked 1
Sub Total Part A 18
Part B
Q1 The adequacy of the amended Project Plan 2
Q2 Description of impacts of each of the changes on duration 4
Q3 Description of impacts of each of the changes on cost 2
Sub Total Part B 8
Part C
Q1 Save baseline 1
Q2 a) Status date set + gridline +
b) Enter sensible status data (up to the gridline only)
c) Screenshot of earned value table + CPI & SPI
0.5
1
0.5
d) Completed status report 6
Sub Total Part C 9
TOTAL 35
Notes:
1. In addition to the marks for the final group submission outlined in the marking guide above,
this assessment item 2 also includes 5 individual sub-deliverables and peer assessment. The
marks for the 5 individual sub-deliverables are recorded separately in Moodle.
2. All marks for this assessment item depend on students making a satisfactory contribution to
the group. If students are not contributing they may be asked to work on the assignment as an
individual and/or have marks adjusted. Both peer assessment and individual submissions will
be taken into account.
3. Sub-deliverables must be submitted on time (and with peer assessments) to be awarded marks.Page | 22
Appendix 1: Status Report Template
This is the status report template that is to be used for Part C.
The information to be entered in the status report is shown in italics.
Project Name: Status Report
Project Manager: (for this assessment item, enter
the names of all members of the group>
Status as of: End of Week:
Earned Value Figures
PV EV AC SV SPI CV CPI BAC EAC VAC
Project Description
Milestone Status
Milestone Description Week
scheduled
(baseline)
Date
scheduled
(baseline)
Week &
data
Reached
M1 Project Start – 1 5/6/17 1 (start),
5/6/17
M2
M3
M4
M5
Status summary (schedule and budget)
Schedule
Planned finish date (from Gantt chart):
Current estimated finish date (from tracking Gantt chart):
The planned cost to date:
The actual cost to date:
Schedule Variance: Page | 23
Summary:
1. < Based on the finish dates in the tracking Gantt chart, explain whether the project is
currently ahead or behind and by how much.>
2.
Budget
The actual cost to date:
The earned value to date:
Cost Variance:
CPI:
Summary:
1.
2.
Explanations
Major changes or issues since last report
Risk watch: