P a g e 1 | 6
CSM80007- CONSTRUCTION SITE
OPERATIONS
FINAL EXAM (excl. OH&S) - SEMESTER 1, 2017
This Examination is part of the assessment for the non OH&S component
(65%) of the Construction Site Operations subject in Semester One (1),
2017. The full details of the assessment of this component were provided, in
writing, at the commencement of the Semester. As a reminder, this
examination is worth 45% of the total marks. Instructions for this
Examination are outlined in Section 4.
Where ‘Contract Administrator’ is used in this Examination paper, it has the
same meaning as ‘Superintendent’ used in AS4000 – GENERAL
CONDITIONS OF CONTRACT. The details of the examination follow.
1. BACKGROUND
Your company (a contracting firm) has been contracted by City of Whittlesea
to construct a Tennis Club Pavilion & associated Works as part of an upgrade
to the services provided in the area. (Yan Yan).
City of Whittlesea is the Client and the funding is provided by grants from
the State Government. The new Tennis Pavilion will assist the community to
engage in leisure activities in the area – where possible, all Sub-Contractors,
day labourers, relevant materials and Plant and Equipment hire are to be
sourced from the local district.
During the ‘Pre-Tendering’ phase, all tenderers had adequate time and
sufficient guidance to thoroughly inspect the site, fully review all the geotechnical information and the detailed plans for the Project and access to all
relevant technical and non-technical data they needed to be fully prepared to
make an informed bid. They were also given an assessment of the availability
and skills of labour in the area as well as the type of material (although
untested) and equipment located there. All tenderers were required to
acknowledge, in writing, that they had appropriate access and professional
guidance to all the necessary information they required to be able to make an
informed bid.
2. FURTHER INFORMATION
A. Construction time for the project was specified as 12 months. AS 4000
has been selected as the General Conditions of Contract for the
project.Page 2 of 6
B. Your company has engaged a site management team (Project
Manager, Contracts Administrator, Site Engineer, Site Foreman,
Accounts Clerk). Client has assigned a Project Manager (Client) to act
as Superintendent and a design engineer to resolve any design issues
during construction. Client also has other stakeholders (local tennis
club; Community leader; Council Member).
C. Early in the construction several errors are found in the plans provided
by the Client. Significant redesign is required before work can
continue. These errors were notified by the Contractor and
Superintendent issued direction to clarify the ambiguities and corrected
the errors. Contractor has submitted claims during first month for
additional cost (estimated additional cost $10,000) but maintained the
time for completion at 12 months.
D. During excavation and preparation of both the ‘green field’ and ‘brown
field’ areas, ‘objects of antiquity’ were uncovered in the area where
tennis pavilion to be constructed. During second month, object of
antiquity was found and it was removed and handed over to the client.
This set back the project by 14 days. Contractor has spent $100,000 in
dealing with the removal of “object of antiquity”
E. During third month, Client decided to change the material for seating
to be used in the pavilion. Your company has already ordered the
material as per original drawing. Superintendent chose to direct the
changes under AS 4000. Estimated additional cost in respect of this
change is $100,000.
F. Your company has made progress and completed 40% of the original
works (earned value) in 6 Months’ time.
G. The weather is ideal for construction – the expectation, based on
previous weather records of the area, had been that up to 10% of the
time could be lost because of adverse weather. This has been built
into the contract price by your company. As at end of 6 months there
has been no claim for EOT in respect of inclement weather.
H. Expenditure Profile (AUD in thousands)
Month 1 2 3 4 5 6 7 8 9 10 11 12
Planned 50 100 120 120 120 130 130 130 120 120 100 50
Actual 60 150 250 120 130 130
Note:
1. Actual cost during first month includes claim for resolving
errors.
2. Actual cost during second month includes claim for dealing
with object of antiquity.Page 3 of 6
3. Actual cost during third month includes claim for change in
design for seating material.
2.EXAM QUESTIONS
Question 1: Project Risk and Communication
a. Your company has been requested by Client to prepare and submit a
communication management plan. Prepare a communication
management plan involving site management team and client’s team
and stakeholders. (4 marks)
b. Client Project Manager prepared a project risk matrix for the project to
prepare the initial project budget. Prepare a project risk for this project.
(4 marks)
Question 2: Application of AS 4000
a. AS4000 details specific lines of communication for the effective
processing of all progress payments (Monthly). Detail this process as
outlined by AS4000, specifically identifying all relevant clauses that
authorise the process. Explain security of payment act and its
application in your claim. (4 marks)
b. Explain how your company submitted the claims for dealing with
ambiguities and errors in the documents with relevant clauses from AS
4000. (4 marks)
c. Your company decided to make ‘Claims for Variation’ for the
additional works arising from the re-design of the seating. Your claim
should include possible surplus material or other alternative ways to
deal with your order. What is the relevant clause under which
Superintendent must have issued the direction to change the seating
material?; explain with reasons. (4 marks)
d. Explain how your company dealt with discovery of ‘object of antiquity’
and how the Superintendent dealt with the claims for additional cost
and time. (4 marks)
e. Your company noticed that the bolts shown on the drawings to fix the
seatings were specified as galvanized iron bolts. Your company
advised the Client that stainless steel bolts would be appropriate to
avoid corrosion. Superintendent is considering your company’s
suggestion. Explain how the Superintendent and your company go
about implementing the change of material for bolt. (4 marks)
Question 3: Earned Value Analysis
a. Based on the information provided in section H and other sections
under “Further Information” carry out earned value analysis at the end
of 6th month and calculate PV; EV; AC; CV; SV; CPI, SPI; BAC
(4 marks)Page 4 of 6
b. Estimate the cost at completion (EAC) using different methods;
I. If the CPI is expected to be the same for the remainder of the
project,
II. If future work will be accomplished at the planned rate; and
III. If both the CPI and SPI influence the remaining work;
(4 marks)
Question 4: Report
a. Prepare a draft monthly report to the client detailing the status of the
project as at the end of 6th month. (4 marks)
Question 5 : Estimating VOWD (Value of Work Done) and Accruals
In a pipeline project, following information has been provided to the Contract
administrator.
Contract Scope: Procure, deliver, install and test 3 Km long 300mm dia
pipeline from point A to point B as shown in the drawings and specification.
Contract period: 8 Months
Bill of Quantities
Description Qty Unit Rate Currency Amount
(USD) Amount (AUD)
Procurement and delivery of 300mm dia pipes
at site
3000 M 300 USD 900,000
Excavate trench and lay the pipe as specified. 3000 M 120 AUD 360,000
Testing of pipeline as specified 3000 M 30 AUD 90,000
Rates are inclusive of overheads and profit.
At the end of 4th month into the project,
40% of pipes have been delivered to the site and accepted by the
Superintendent as complying with the specification.
Contractor has laid 20% of the pipes and tested 50% of the laid pipes.
Invoices for 30% of delivery of pipes (3KM total); 15% of pipe in place;
0% for testing have been paid at the end of 3rd month.
Exchange rate for the end of 3rd month; 1AUD = 0.75 USD as paid in
invoices.
Exchange rate for the end of 4th month (as provided by finance department);
1AUD = 0.80 USD
a. Estimate the VOWD (in AUD) as at end of 4th month and accrual
(accounting) (in AUD) . (5 marks)Page 5 of 6
4. EXAMINATION INSTRUCTIONS
a. Please read the paper and the questions carefully. Each of the
five (5) questions must be answered - specific marks are
allocated to each question and, if relevant, to the elements of
each question. Therefore, it is imperative that you read all the
‘Background’ and ‘Further Information’ carefully, at least a
couple of times, before you commence your responses to any of
the questions. Background and Further information are
relevant for first four questions and question 5 is to be
attempted without reference to the background and further
information.
b. You may wish to create additional background material and/or
assumptions about your company’s Project to assist in
developing your responses. However, if you do so, you must
clearly outline what additional background information you have
created at the very beginning on Page 1 of your response prior
to answering any of the questions.
c. The response should be no more than 1500 words including
any Appendices.
d. References are to be used with the author and source clearly
stated and included as either a ‘bibliography’ at the end of your
paper or in ‘footnotes’ at the bottom of the relevant page.
e. A hard copy is to be delivered no later than 5.00pm, Friday
19th May 2017 at the address in (f) below.
f) The hard copy response is to be delivered, by the due date, to: -
Box 44 Sungkon Moon Mail Box, 7th Floor, Advanced
Technologies Centre (ATC Building),
Burwood Rd., Hawthorn, 3122
NOTE: Only a hard copy will be accepted as formal
submission. You can send an email version for
information purpose ([email protected]). It
will be considered only for information purpose.
Acknowledgement of receipt of your paper will not
be provided.Page 6 of 6
g) The examination is to be done in your own time and no
collaboration is to be entered into with any other person,
particularly your fellow or past students. Plagiarism and/or
copying of any form are considered serious offences by
Swinburne University of Technology and, if detected, usually
result in immediate disqualification.
End.