Business Case Title  Subtitle  Department Title  [This should be the publication title for the initiative,   if it were to be funded in the budget process.]  [Please note:  1. This template can be used for both capital and output proposals with  modification for output initiatives as appropriate.  2. When completing this template you should refer to the investment  lifecycle and high value/high risk guidelines and associated technical  guidelines for more detailed explanations.   3. The extent of detail should be scaled to the relative complexity of the  proposal and some areas may not be relevant for all proposals.  4. The project options analysis (Section 4) requires a consistent  methodology applied to analysis of options with a level of accuracy  consistent with ‘concept estimate’ at a minimum. The analysis should  be evidence based and defensible with estimates of capital costs, cash  flows and ongoing output or operating costs sufficient to robustly  compare options.  5. The recommended solution (Section 5) requires a detailed cost build‐ up with significant rigor based on a design brief or project scope  statement. Accuracy of information in relation to the recommended  solution should be at a level of accuracy consistent with that of a  ‘preliminary design estimate’.  6. Any text included in [ ] is for guidance only and should be deleted.  7. Forward any comments to [email protected]]     Contents  Executive summary ..............................................................................................  1  1.  Part 1 Problem ..........................................................................................  2  1.1  Background  ........................................................................................................................  2  1.2  Definition of the problem  ..................................................................................................  2  1.3  Evidence of the problem....................................................................................................  2  1.4  Timing considerations  ........................................................................................................  2  1.5  Consideration of the broader context  ...............................................................................  3  2.  Part 2 Benefits  ...........................................................................................  4  2.1  Benefits to be delivered  .....................................................................................................  4  2.2  Importance of the benefits to Government  ......................................................................  4  2.3  Evidence of benefit delivery ..............................................................................................  4  2.4  Interdependencies  .............................................................................................................  4  3.  Part 3 Strategic response  ..........................................................................  5  3.1  Method and criteria  ...........................................................................................................  5  3.2  Strategic options analysis ..................................................................................................  5  3.3  Recommended strategic option ........................................................................................  8  4.  Part 4 Project options analysis  ..................................................................  9  4.1  Project options considered  ................................................................................................  9  4.2  Stakeholder identification and consultation .....................................................................  9  4.3  Social impacts ..................................................................................................................10  4.4  Environmental impacts  ....................................................................................................10  4.5  Economic impacts  ............................................................................................................10  4.6  Overall evaluation of socio‐economic and environmental impacts  ................................10  4.7  Financial analysis .............................................................................................................11  4.8  Risk comparison  ...............................................................................................................11  4.9  Integrated analysis and options ranking  ..........................................................................11  5.  Part 5: Deliverability of recommended solution  .....................................  14  5.1  Details of recommended solution ...................................................................................14  5.2  Commercial and financial ................................................................................................14  5.3  Management ...................................................................................................................17  5.4  Delivery  17  Appendix A: Benefit Management Plan .............................................................  19  Appendix B: Financial data presentation  ............................................................  20  Appendix C: Sign‐off checklist ............................................................................  22     Business Case Title  Subtitle  1   Executive summary  [The Executive Summary is an essential stand‐alone part of a full business case highlighting the  overall story and key points of the Full Business Case. While the Executive Summary is the first  section of the full business case, it is often the last area completed.   It should be a clear and concise plain‐English outline of the whole proposal and as a guide less than  10 pages long. Include summary tables if appropriate e.g. to establish context.  The Executive Summary should:   Describe the investment proposal in one to two sentences.   This detailed business case seeks formal approval to invest $[xxx] million in [20yy/yy] to ……….....  (This should include both capital and output factors including ongoing resourcing and expected  outcomes.) (Note: This description should serve as the summary description required for budget  publications.)   State what decision‐makers are being asked to consider or decide and, if relevant, any recent  history of consideration such as the strategic case.    Identify any overarching contextual factors  For example specify if the proposal is related to an election commitment and provide a brief  overview of how the proposal relates to that commitment.  If the proposal is extension or  subsequent stage of an existing investment outline the previous funding or commitment and its  impact to date.   Briefly identify the different options considered and a summary of the evaluation of those options  (including a summarised options ranking table).  The Executive Summary needs to convey that the investment proposal:   meets an important need   is supported by strong strategic and policy merit;   optimises value for money from a whole of life perspective; and   is achievable i.e. it can be delivered on‐time and on‐budget and will realise the intended benefits  it sets out to achieve.  Where a proposal faces considerable uncertainty the executive summary and business case should  convey options to flexibly deal with that uncertainty rather than lock‐in a complete solution too soon.  At the end of the Executive Summary, insert updated Investment Concept Brief (including Investment  Logic Map) if available.  Provide reference to key supporting documentation. Add any key documents or extracts to the  Appendix of the full business case. ]   2  Department Title    1. Part 1  Problem  [For output proposals the full business case is likely to be the first presentation of the proposal to  government. Given this, the Stage 1: Conceptualise guideline may assist in characterising the  ‘problem’ for the purpose of this Part.  For asset proposals this Part should revisit and confirm the currency of the analysis of the problem in  the earlier strategic business case (strategic assessment or preliminary business case).  This will  involve re‐presenting the information from the strategic business case, reassessing its validity and  further substantiating the existence of the problem with evidence where appropriate. The intent is  to strengthen the case for the problem, and briefly outline any significant changes since the strategic  business case.  Remember that a ‘problem’ can include a service need, issue, or lost opportunity. For further  information on populating this Part for asset submissions see the Stage 2: Prove guideline.]  1.1 Background  [Describe the context and background necessary to set the scene to introduce the problem and  benefits from addressing the problem. Outline the existing service related outputs, existing asset  base and resource commitments including lapsing status. This might include a discussion on the need  for government intervention and role of government, current service funding, service distribution  and levels, and underlying drivers of those services. This section may also introduce providers and  stakeholders relevant to the problem. ]  1.2 Definition of the problem  [Explain in plain English and in less than one page the problem(s) needing to be solved. Present the  cause of each problem, who is affected, and how they are affected. Describe the nature of the  problem for example whether it is immediate, transitory, ongoing or escalating. ]  1.3 Evidence of the problem  [Provide the evidence of both the cause and effect of the problem. Evidence might include:   demand forecasts with assumptions;   key performance indicators (KPIs) on current performance levels; and/ or   facts/examples of the problem.]  1.4 Timing considerations  [Describe why the problem needs to be solved by government at this time, noting any connections to  long‐term planning documents. Explore whether the problem is suited to a staged response. Explain  the implications of delaying a response to the defined problem such as:    physical or capacity limits will be reached   significant reductions in the level of service (quality/quantity) will be experienced   failure to meet specific government commitments or legislative requirements   requirement for urgent action at additional cost due to asset failure, system overload etc;    lead time for investment to become operational; and   any critical dependencies with related service requirements.]   Business Case Title  Subtitle   3   1.5 Consideration of the broader context  [Explain whether similar needs or opportunities exist either inside or outside your organisation that  might be addressed together with this proposal. For example, benefits of a wider sectoral approach,  integration opportunities, pilot studies in other sectors that may impact the type of response.]   4  Department Title    2. Part 2  Benefits  [For asset proposals this Part should revisit and confirm the currency of the analysis of the benefits in  the earlier strategic business case (strategic assessment or preliminary business case).  This will  involve re‐presenting the information from the strategic business case, reassessing its validity and  further substantiating the evidence of benefit delivery where appropriate. The intent is to  strengthen the case for the benefits, and briefly outline any significant changes since the strategic  business case.  For agencies using the Investment Management Standard to map benefits, note that not all benefits  identified as part of an investment logic mapping process will be suitable for inclusion in an economic  evaluation of an investment proposal. Economic evaluations focus on welfare impacts on society  rather than agency specific impacts and transfer benefits. Economic benefits which would be suitable  for inclusion in economic evaluations are typically specific, tangible, and able to be monetised and  can be linked unambiguously to an investment or activity. DTF can provide case‐by‐case guidance to  agencies on this issue as needed.]  2.1 Benefits to be delivered  [Explain the key benefits that flow if the problem is solved. (These can be drawn from the investment  logic map and benefit map if available.)   List key high‐level economic, social and environmental benefits the initiative will deliver. Any dis‐ benefits or negative consequences resulting from addressing the problem must be outlined  clearly.]  2.2 Importance of the benefits to Government  [Show how this investment will help to advance the government and/or organisation to meet its  objectives. This might include reference to the size and timing of those benefits.  Describe how this initiative connects to government priorities and the department’s corporate,  strategic and long term planning documents.]  2.3 Evidence of benefit delivery  [Define the measures and key performance indicators that will show whether the benefits have been  delivered. These benefits provide evaluation criteria and objectives for the development and  selection of interventions and options.  Details of baseline, interim and target measures, dates for the KPIs and the person/position  responsible for delivering the benefits should be included in an appended benefit management plan  or equivalent, which has been updated to reflect the recommended option. Reference or include the  benefits management map.   Where appropriate (as an alternative to a Benefit Management Plan) an evaluation  strategy/framework should be included or attached. ]  2.4 Interdependencies   [Identify key interdependencies critical to benefit delivery. For example reliance on other projects or  decisions. These interdependencies may require a level of flexibility to be built into the proposal.]     Business Case Title  Subtitle   5   3. Part 3  Strategic response  [For asset proposals this Part should revisit and confirm the currency of the analysis in the earlier  strategic business case. This will involve re‐presenting the information from the strategic business  case, reassessing its validity and further substantiating the evidence, feasibility and assessment of  the strategic options analysis process. The intent is to strengthen the case for the preferred  ‘strategic response’, and briefly outline any significant changes since the strategic business case.    3.1 Method and criteria  [Outline the method and criteria used to select the strategic response. Criteria should include the  extent to which interventions will achieve the proposed benefits and offer value for money. Identify  assumptions and constraints used to inform the development of strategic options.]  3.2 Strategic options analysis  3.2.1 Strategic interventions  [Explain the potential strategic interventions.   Describe and provide evidence or reasoning as to why these interventions might have an impact.  The table may be used to outline strategic interventions. Note it is not mandatory.]  Strategic Interventions  Intervention 1  Intervention 2  Intervention 3  Intervention 4  Intervention 5  Intervention 6  Intervention 7  Intervention 8  Intervention 9  Intervention 10  Table X Summary of potential strategic interventions  [The number of strategic interventions that should be considered depends on the scale and  complexity of the problem/investment.]     6  Department Title    3.2.2 Strategic options  [Explain how the strategic interventions can be packaged into strategic options. This can be imported from the preliminary business case, provided that ongoing currency of  information has been revalidated. The table may be used to outline strategic interventions. Note it is not mandatory.]    Strategic options    Option 1   Option 2  Option 3  Option 4  Option 5  Option 6  Strategic Interventions              Intervention 1              Intervention 2              Intervention 3              Intervention 4              Intervention 5              Intervention 6              Intervention 7              Intervention 8              Intervention 9              Intervention 10              Table X: Strategic options  [Listed in the left‐hand columns are strategic interventions that could respond to the identified problem and deliver the expected benefits (and their KPIs). Against the listed  strategic interventions, a spread of strategic options should be structured to provide genuine alternative strategic responses to the problem. These are in the right‐hand  columns. Shade boxes and allocate percentages to shaded boxes to indicate the relative importance of each specific intervention within the option. To decide on the  importance of each specific intervention within the option, balance two factors: the importance of the intervention in developing the KPIs and the likely cost/effort involved.]  Business Case Title  Subtitle   7    3.2.3 Ranking of strategic options  [Evaluate the strategic options to determine the proposed strategic response. This can be imported from the preliminary business case, provided that ongoing currency of  information has been revalidated. Provide evidence to support this high level assessment. The table may be used to outline strategic interventions. Note it is not mandatory]    Strategic options    Option 1  Option 2  Option 3  Option 4  Option 5  Option 6                Benefits  Percentage of full benefit to be delivered  0%  0%  0%  0%  0%  0%  Benefit 1    %              Benefit 2    %              Benefit 3    %              Cost                  Estimated capital investment cost (Range)  $n mil ‐ $n mil  $n mil ‐ $n mil  $n mil ‐ $n mil  $n mil ‐ $n mil  $n mil ‐ $n mil  $n mil ‐ $n mil  Estimated operational costs (Range)  $n mil ‐ $n mil pa  $n mil ‐ $n mil pa  $n mil ‐ $n mil pa  $n mil ‐ $n mil pa  $n mil ‐ $n mil pa  $n mil ‐ $n mil pa  Time  (Range)  mm‐mm  mm‐mm  mm‐mm  mm‐mm  mm‐mm  mm‐mm  Risks  Risk 1        Risk 2        Dis‐benefits  Dis‐benefit 1        Dis‐benefit 2        Ranking  1‐3              Table X: Evaluation of strategic options  [Costs here are indicative/order of magnitude and do not need to be precisely calculated, but need to be reasonable estimate of likely financial impact of each option.]   8  Department Title    3.3 Recommended strategic option  [Present the recommended strategic option, summarising the response and the rationale behind its  selection. For example, the recommended option may have been selected because it provides a level  of flexibility required to deal with uncertainty surrounding the problem. ]     Business Case Title  Subtitle   9   4. Part 4  Project options analysis   [Accuracy of data used to compare project options should be sufficient to robustly compare options.  Analysis of project options requires a level of accuracy consistent with ‘concept estimates’ (at a  minimum) of capital costs, cash flows and ongoing output or operating costs. A concept estimate is  an approximation of the probable cost of a program or project based on available verifiable  information. The level of accuracy used to present estimates should reflect the scale and complexity  of the investment. The level of analysis  should provide sufficient information for an effective  comparison of the project options and to demonstrate that an adequate range of options have been  considered. The methodology used should be consistent across all options. Indicative costs should be  supported by evidence and defensible.  The tables in this section are a guide only and should be used, modified or not used as appropriate.  Projects which are HVHR should provide more detailed information to support assessment of  robustness.  In characterising the project options and considering their impacts, agencies should address  sustainability investment opportunities of project options. For example where significant  operational savings can be derived through specific approaches. The focus should be to identify up‐ front sustainability investments in areas of need and which are likely to deliver a good investment  return.  Further information  For more information on completing this section see the:    Stage 2: Prove guideline.   Technical guideline: Sustainability investment guidelines for Victoria’s public assets.]  4.1 Project options considered  [Expand each of the ‘strategic interventions’ included in the ‘strategic response’ into several more  detailed potential project options, including a ‘base case’ and at least one ‘market based solution’.  Aim for a maximum of around five. Refer to the Stage 2: Prove guideline for an explanation of the  base case and market based solutions.   Describe the method and rationale used to select the project options   Describe project options, including:    scope   asset and output options (or combinations);    at least one market‐based solution where possible;   potential for 3rd  party revenues;    critical assumptions or constraints (or windows of opportunity) of each option;   outline any project options considered but not evaluated and state rationale for non‐ consideration; and   at a high level, the extent to which each of the feasible options conforms to Government and  relevant agency legislation, policies, standards and strategies.]  4.2 Stakeholder identification and consultation   [At a broad level, provide an overview of the likely relative impact on key stakeholders of the various  project options, and outline their position in relation to the project.]   10  Department Title    4.3 Social impacts    [Outline the social impacts and opportunities of the proposal and identify any significant social issues  specifically relevant to particular project options (i.e. differentiating between the project options).]  4.4 Environmental impacts  [Provide a high‐level overview of the relative environmental impact analysis of the options including  specific actions required to meet all relevant legislative requirements and identified likely community  concerns.]   4.5 Economic impacts  [Provide a high‐level overview  of all significant economic impacts and opportunities of the options.  ‘Economic impacts’ in this case refers to impacts on key economic variables, such as value‐add,  productivity, workforce participation, unemployment and others.    This could be done in a qualitative manner (e.g. by describing possible changes and their likely order  of magnitude), or through actual economic modelling to come up with robust quantitative estimates.  The later should only be done where the magnitude of the project warrants this additional effort.   There is a wealth of data available from the Australian Bureau of Statistics and other sources, which  can assist in this endeavour – particularly when providing qualitative descriptions of possible impacts.    Where the magnitude of the project warrants providing quantitative estimates, then Computable  General Equilibrium (CGE) modelling is recommended. Like all modelling, this needs to be based on  robust assumptions/inputs that are transparent in order for it to be seen as reliable.]  4.6 Overall evaluation of socio‐economic and environmental impacts  [The expected socio‐economic and environmental impacts of the project options need to be assessed  and consolidated within a robust framework that appropriately captures and weighs these impacts.  The assessment of socio‐economic and environmental impacts is very important because it  effectively outlines what the Government would be ‘purchasing’ for its investment (in terms of the  net benefits to society).  The preferred methodology for integrating social, economic and environmental impacts is a cost‐ benefit analysis (also known as an ‘economic evaluation’). This may be combined with a multi‐criteria  analysis for impacts that are unsuited to the cost‐benefit analysis framework, such as where benefits  are difficult to monetise,. These tools should enable all key impacts to be captured in the  assessment.]  4.6.1 Cost benefit analysis (economic evaluation)   [Identify welfare impacts on society, both costs and benefits, for each project option – these impacts  include both market and non‐market specific impacts in the areas previously described as social,  environmental and economic. Describe the methodology to be used; in general this will be a net  present value assessment at an aggregate level relative to the base case. Quantify and monetise costs  and benefits at the level of accuracy of  ‘concept estimate’ to ‘developed concept estimate’. Note  that the level of accuracy should be determined based on the scale and complexity of this  investment. Assumptions should be provided to justify estimates used.  Once costs and benefits have been estimated, agencies should discount impacts back to present  values and rank the project options. Note distributional impacts, while an important factor for  government decision‐making, are not included in the headline results (e.g. the net present value) of  the economic evaluation (which addresses welfare impacts to society as a whole).   For further information on completing this part see Stage 2: Prove guideline.  Outline the outcome of the economic analysis.]     Business Case Title  Subtitle   11   4.7 Financial analysis  [Provide an estimate of the capital and whole life (output) costs of the project options and describe  the process by which the estimate was derived (e.g. workshop, previous project). Costings for this  section of the full business case are at ‘concept estimate’ level at a minimum, and not extensively  detailed, but should consider whole‐of‐life differences between options over an appropriate period.  They need to be a reasonable evidence‐based realistic estimates but are not intended to be  comprehensively constructed from first principle. They need to provide sufficient detail to allow the  Net Present Value (NPV) comparison of options.  The analysis should allow decision‐makers to consider the option that will deliver the best outcomes  in line with government objectives, including Budget considerations, and will have a demonstrable  effect on output/service delivery performance.]  4.8 Risk comparison  [Risk assessment here is high level and needs to be sufficient to enable relative comparison of  options.  Describe risk assessment process for the project options analysis, which may include a risk workshop.  Risks identified should consider the financial, economic, social and environmental analyses.  Provide a summary of key risks which are critical to differentiate the success of the investment in  relation to the project options considered. Significant uncertainties may warrant a different approach  to the investment to incorporate flexibility to manage the uncertainty.  To assist in identifying the key risks to consider, the following is a (non‐exhaustive) list of risk  categories: Change in law/policy; commercial; commissioning; completion/construction; contractual;  demand; economic; environmental; financial; implementation; investment planning; management;  obsolescence; operations; organisational; political; private sector; regulatory technological; residual  value; upgrade.]  4.9 Integrated analysis and options ranking   [This section summarises at a high level the relative merits of the options considered.  Details in this  section are expected to be at a conceptual level only.   To the extent that costs, benefits and risks have been quantified and valued robustly, the preferred  option is typically the one with the highest, risk adjusted, NPV.   As the headline result of the economic evaluation does not include distributional impacts or where a  project option has significant intangible (or non‐monetised) benefits, these impacts can out‐weigh  the difference in NPV between alternative options. This can alter the choice of the preferred option  and these trade‐offs need to be clarified for decision‐makers. Multi‐criteria analysis (MCA) can be a  useful tool to do this.  Selection of options can be affected by the risk/uncertainty assessment. Further, where the NPV of  an option is subject to significant uncertainty, it can be difficult to distinguish between alternatives. A  low risk, low NPV option may be preferred to an alternative with higher but more uncertain net  benefits. The level of uncertainty may suggest that flexibility needs to be built into the recommended  approach, for example allowing decisions to be made progressively as more information becomes  available.  In a summary table, provide an integrated assessment of financial and non‐financial impacts to arrive  at a ranking of project options. Where a multi‐criteria analysis is included in the integrated  assessment, outline the relative weighting of the financial and non‐financial components.   See two alternative examples of possible financial and socio‐economic analysis summary tables  below. Note, choose which table of these two options is most appropriate to your integrated  analysis. Do not fill out both.]       12  Department Title      Table xx: Presenting the results of the options analysis    Project option  1: Do Nothing  Project  option 2:  Project option  3:  Project option  4:  Project option  5:  Analysis Period (years)       Capital Costs ($m)       Output Costs ($m)       Cost‐Benefit Analysis (of monetary costs and benefits discounted at the appropriate Discount Rate)  Present Value of Benefits  ($m)        Present Value of Costs  ($m)        Benefit Cost Ratio        Net Present Value ($m)       Other important considerations (see the examples provided)  Intangible costs / benefits  (e.g. small, med., large)        Distributional impacts  (e.g. small, med., large)        …       Preferred option              Table xx: Presenting the results of the options analysis, with multi‐criteria analysis     Project option  1: Do Nothing  Project  option 2:  Project option  3:  Project option  4:  Project option  5:  Analysis Period (years)       Capital Costs ($m)       Output Costs ($m)       Cost‐Benefit Analysis (of monetary costs and benefits discounted at the appropriate Discount Rate)  Present Value of Benefits  ($m)        Present Value of Costs  ($m)        Benefit Cost Ratio        Net Present Value ($m)       Multi‐Criteria Analysis (ranking of intangible costs and benefits, if any)  Criteria 1       Criteria 2       Criteria 3       Preferred option            4.9.1 Testing the robustness of the options analysis   [Conducting a sensitivity analysis is a form of quantitative analysis to examine how net present  values, benefits, costs or other outcomes vary as individual assumptions or variables change. This  approach may be used to test the robustness of the project options analysis, particularly for larger  investments.  Provide a high level summary of the key assumptions for the options assessment.  Provide a  description on the robustness of the options analysis in relation to key assumptions made.     The table below is optional.]     Table xx: Sensitivity testing results ‐ Scenario One: ………………………….   Business Case Title  Subtitle   13     Project option  1: Do Nothing  Project option  2:  Project option  3:  Project option  4:  Project option  5:  Analysis Period (years)       Capital Costs ($m)       Output Costs ($m)       Cost‐Benefit Analysis (of monetary costs and benefits discounted at the appropriate discount rate)  Present Value of  Benefits ($m)        Present Value of Costs  ($m)        Benefit Cost Ratio        Net Present Value ($m)       Other important considerations or Multi‐Criteria Analysis (ranking of intangible costs and benefits, if any)  Criteria 1       Criteria 2       Criteria 3       Preferred option               14  Department Title    5. Part 5: Deliverability of recommended solution  [The full business case is the first time departments are asked to address the information required in  Part 5 and speaks to the question: ‘Can the solution really be delivered?’, this section is a key part of  the full business case and should put forward a rigorous case clearly justifying why the recommended  solution is the most effective and actionable solution.  This section should include confirmation of the above analysis in the light of detailed costing and  scoping of the recommended solution as well as additional detailed information relating specifically  to the deliverability of the recommended solution, as specified below.   To avoid duplication, refer to earlier sections where appropriate.   This section should also justify why the recommended solution is preferred in relation to each  component of the analysis.]   5.1 Details of recommended solution  [Clearly state which project option (which may comprise one or a number of projects) is the  Recommended Solution, addressing the rationale for its selection in light of the integrated  assessment, stating its details (including objectives and a project scope statement).   If a major asset is required, provide a brief summary of the design and specifications to the extent  they have been developed. Note: detailed designs are not expected at this stage, however  departments must provide enough information on scope to support a rigorous costing.  Provide details on output requirements associated with changes proposed to service delivery  including VPS and non VPS staffing implications.  Where appropriate include a summary of key elements of the design feasibility study which  demonstrates the long term vision for the preferred option in the broader urban/environmental  context. Provide a ‘Design Intent Statement’ to demonstrate the intended level of design quality and  identify what design aspects of the project need special consideration.  Provide information on preferred sequencing or staging of the project solution and justify why  staging/ sequencing is required or desired.  Describe significant broader impacts specific to the implementation of the Recommended Solution.  Indicate locational details and service area impacts.  Outline how the solution is consistent with, or addresses, public interest issues such as equity, access  etc.]  5.2 Commercial and financial  5.2.1 Procurement  [Outline the procurement options analysis ‐ method and process, showing ranking of options against  criteria used to selected recommended procurement strategy.   Detail the recommended procurement strategy for this investment, justifying why it is the best value‐ for‐money option, for example due to its capacity to include flexibility or better manage risk. This  should be balanced with the related issues of time, cost, whole of life value and quality.  Outline the organisation’s experience and capability to deliver the preferred procurement method as  well as key risks and contractual issues. (Include strategy to address deficiencies where appropriate  for example intention to engage expert help.)   Business Case Title  Subtitle   15   Formulate adaptations to the preferred procurement method to ensure that quality and good design  are embedded in the process. The Office of the Victorian Government Architect can provide advice  on the selection of procurement models and potential adaptations and the design, site utilisation etc.  If a PPP procurement approach is being proposed the Partnerships Victoria Group at DTF can advise  on the additional details required.  If project alliancing is being considered, full business case requirements are different, please contact  DTF Commercial Division for further advice or consult the National guidelines.]   5.2.2 Risk assessment and management  [Provide a detailed risk assessment of the recommended solution, outlining key risks and  management strategies.]  Risk  Management strategy  [Describe risk]  [Outline strategy for management]      Table X: Key risks to the success of this investment  [The risks may highlight the need for a flexible approach to the investment. For example where the  uncertainties may be resolved at a point in time (e.g. success or failure of a pilot study) and flexibility  can be built in to allow an informed decision at this time (whether to proceed with the full  investment). This section should describe ‘desired flexibility’ and ‘circumstances which make  flexibility desirable.’  Provide an overview of proposed arrangements for ongoing risk monitoring and management.  Include appendix with risk management strategy and risk register.]   5.2.3 Detailed costing and economic evaluation  [Provide a detailed overview of the costing for the Recommended Solution, including capital TEI and  output costs. Include budget cash flow over a relevant period for both capital and output amounts.   The project budget estimate including: base cost estimate, base risk allocation and contingency  should be based on a project scope statement at the preliminary design estimate level.  Identify the impact on output funding and the breakdown of operating costs to key components such  as staffing, maintenance, depreciation, CAC etc. This detail should extend over a reasonable period of  years to allow a whole of life costing perspective.   Attach appropriate tables in the appendices, refer Appendix B for example tables.  Departments should consult with DTF to agree costings before submitting the business case for  Budget funding consideration.  For Asset projects:  Refer to the Investment Lifecycle’s Project Budget Guideline which provides specific guidance on  development of the project budget. The tables below are based on that guidance and may be  modified to incorporate appropriate details.]    Element  Estimate  Table reference  Base cost estimate  $XXXm  (Table 2)  Base risk allocation  $XXm  (Table 3)  Project cost estimate  $XXXm   Contingency  $XXm  (Table 3)  Project budget  $XXXm   Table 1: Headline project cost element summary     16  Department Title    BASE COST ESTIMATE  Effective date of BCE: dd/mm/yy  Estimated date of commencement of construction: dd/mm/yy  1  Direct Costs      1.1  Materials      1.2  Labour      1.3  Plant Hire      Sub total    $  2  Indirect Costs      2.1  Recurrent overheads       2.1.1  Site facilities      2.1.2  Plant & Equipment – site maintenance      2.1.3  Project management costs      2.1.4  Commercial      2.1.5  QA and Safety     2.2  Non‐recurrent overheads       2.2.1  Establishment and mobilisation      2.2.2  Disestablishment and demobilisation       2.2.3  Project insurances      2.2.4  Professional fees  – design, legal, financial, etc     Subtotal    $  3  Owner’s Cost      3.1  Contracted professional staff     3.2  Investigations      3.3  Land costs & resumptions      3.4  Authority fees      3.5  Owner supplied plant and equipment     Subtotal    $  4  Contractor’s Fee      4.1  Profit margin      4.2  Corporate Overheads      Subtotal     5  Provisional Sums      5.1       Subtotal    $  TOTAL OF BASE COST ESTIMATE  $  Table 2: Base cost estimate  BASE RISK ALLOCATION AND CONTINGENCY    6  Base Risk Allocation       6.1  Escalation  (period between BCE and construction)     6.2  Project Risk A      6.3  Project Risk B etc      Sub total    $         7  Contingency       7.1       Subtotal    $  TOTAL OF PROJECT RISKS  $  Table 3: Project risks    [The Net Present Value estimate should be recalculated based on the refined costs and a more  developed assessment of the benefits for the recommended solution. For the recommended solution  agencies may need to invest in valuation techniques such as market based valuation, revealed  preferences, stated preference or benefit transfer method to better assess the monetary value of  benefits. Note: this should only be undertaken if the additional effort and expense incurred in  assigning monetary values reflects the likely size of those impacts.     Business Case Title  Subtitle   17   Based on the detailed costing of capital, outputs and benefits for the recommended solution  formalise the economic analysis (e.g. NPV and BCR) to demonstrate the economic impact of the  investment.]  5.2.4 Funding sources  [Discuss proposed funding sources including potential contributions from other levels of government,  private sector, sale of assets etc. This section should present a summary of the sources of funding  requirement for capital and output costs which will be required for budget deliberations. This should  include offsets or the consequences of adopting a market based solution. Typically this presents  budget and forward estimates with a balance of TEI and ongoing output funding.  Refer Appendix B  for examples of how this information might be presented.]  5.3 Management   5.3.1 Governance  [For the recommended solution, detail the proposed project governance structure demonstrating its  appropriateness. Note: For HVHR projects, DTF must be included in the project governance structure.  A Senior Responsible Owner needs to be identified (or proposed for all investments.]  5.3.2 Stakeholder engagement and communications plan  [Provide detailed information about key stakeholders in relation to the recommended solution.   Provide an outline of key elements of stakeholder and communications analysis describing  stakeholders, their likely position on the project and plans to manage that. If available attach as an  appendix a proposed high‐level stakeholder engagement and communications strategy covering the  approach to dealing with stakeholders both upon project announcement and ongoing during project.]  5.3.3 Project management strategy  [Outline the proposed project management strategy demonstrating its suitability and robustness,  appending any detailed plans as an appendix if necessary.   Describe the organisational capability and generic systems, standards and methodology which would  allow the project to be delivered successfully.  Demonstrate in this section that the implementing organisation has the capacity and capability to  mobilise and deliver this investment.]  5.4 Delivery  5.4.1 Change management   [Outline the scope of organisational/process change management required to effectively deliver the  benefits. This may involve process re‐engineering, staff retraining etc. required to transition from  existing arrangements to support the operation of the new investment. If change management  requirements are significant consider appending an outline of the change management strategy.  Note this does not include management of proposed scope changes during implementation.]  5.4.2 Timelines and milestones  [List the major milestones and deliverables and their delivery timelines and contingencies.   Outline the high‐level project schedule, including procurement steps and statutory approvals and key  decision points for project progression, termination or otherwise.  Provide information on potential competing priorities, dependency analysis, skills, capabilities,  availability of agency staff etc.   Provide advice on public communication of project timelines (to be consistent with communications  strategy).]   18  Department Title    5.4.3 Performance measures  [Provide a statement of investment benefits. Analyse how well the recommended solution addresses  the problem and key benefits. This section addresses the effectiveness and efficacy of the proposal.  Provide references to the evidence of benefit delivery identified in section 4 and provide further  specific information on performance measurement for the proposed project, this should be a  detailed description of:    how well the recommended solution delivers identified benefits; and    the specific KPIs that relate to the recommended solution.   Refer to the appended updated benefit management plan to inform this section.  Most investments will affect output performance measures. The impact on existing outputs and  performance measures should be specified indicating both the changes to output metrics relative to  current levels and the timing of that impact.]  Output name:  Performance Measures    Unit of  measure    Change in target if proposal is endorsed  2012‐13      2013‐14      2014‐15      2015‐16      2016‐17  Quantity    Quality    Timeliness    5.4.4 Readiness and next steps  [Explain plans to transition the investment to the next stage (Stage 3: Procure)   Explain the main areas of uncertainty to be resolved in the next stage, for example, information  regarding staffing, approvals, and land acquisition etc.]  5.4.5 Signoff  [Signoffs are required by:    Primary author   The senior responsible owner (or departmental Chief Financial Officer) on Gateway’s Project  Profile Model (PPM) included to update proposal risks.    The senior responsible owner (or Chief Financial Officer) and the department’s Secretary – these  are required for full business cases to be considered by the Government.   In establishing the project budget estimate the SRO should sign off on:    The statements of the service benefits and project scope.   The adequacy of the project budget including the base cost estimate, risk assessment, base risk  allocation and contingency.   This should be supported by additional sign offs from:  – The base cost estimator; and  – The agency and its advisers on base risk allocation and contingency.  Provide details of any review process (e.g. for HVHR Gateway reviews are mandatory).   So that decision‐makers know that the business case is thorough and complete, please provide a  quality assurance checklist such as set out in Appendix C, with business case submissions seeking  endorsement from departmental Secretaries. See the Stage 2: Prove guideline for more details.]  5.4.6 Exit strategy  [Detail the exit strategy and the factors that would lead to wanting to exit either early or at term.  Investments maybe time limited or may involve pilot studies. This section allows for consideration of  what termination rights are desirable at key review or decision points for example lapsing programs.]   Business Case Title  Subtitle   19   Appendix A: Benefit Management Plan  [‘Paste Special’ as an ‘Enhanced Metafile’ for optimum picture quality.]  Include a benefit management or evaluation plan if available or complete the following table for each  KPI. ]  KPI    Baseline    Source    Interim target    Reporting forum   Start date    Frequency    End date    Responsibility              20  Department Title    Appendix B: Financial data presentation   The following tables are intended as a guide to data inclusion and should be used or supplemented as  appropriate. Operating costs should be addressed over a reasonable period to allow a whole of life  perspective – in an appropriate table. Modify tables as required, for example by adjusting period to  capture output costs from commencement of the operation of new facility.   B.1 Funding history  In the table below provide details of the funding history for this or similar/related initiatives. This  table should include funding for an earlier stage in a multi‐stage project, funding for business case  development or scoping study, funding for a lapsing program, or funding for a related program that  has broadly the same policy objective as this initiative.  Description of funding provided  2008‐09  $m  2009‐10  $m  2010‐11  $m  2011‐12  $m  2012‐13  $m                       B.2 Existing funding base  In the table below provide details of the existing funding base that has been provided for this or  similar/related programs. This should include funding that is in the department’s base as well as  funding for any related lapsing programs.  Description of funding provided  2012‐13  $m  2013‐14  $m  2014‐15  $m  2015‐16  $m  2016‐17  $m                       B.3 Budget impact –     2012‐13  $m  2013‐14  $m  2014‐15  $m  2015‐16  $m  2016‐17  $m  TEI  $m  capital funding  Estimated asset investment cash  flow         (Component a)   0.000  0.000  0.000  0.000  0.000  0.000  (Component b)   0.000  0.000  0.000  0.000  0.000  0.000  (Component c)   0.000  0.000  0.000  0.000  0.000  0.000  Sub total (gross asset price increase)  0.000  0.000  0.000  0.000  0.000  0.000  Funds from other sources (e.g. asset  sale proceeds, Commonwealth  funding, trust accounts) – please  specify  (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  Net Impact on capital appropriation  0.000  0.000  0.000  0.000  0.000  0.000  output funding   Price change requested for  provision of output         (Component x) gross output price   0.000  0.000  0.000  0.000  0.000  0.000   Business Case Title  Subtitle   21     2012‐13  $m  2013‐14  $m  2014‐15  $m  2015‐16  $m  2016‐17  $m  TEI  $m  (Component y) gross output price  0.000  0.000  0.000  0.000  0.000  0.000  Capital asset charge  0.000  0.000  0.000  0.000  0.000  0.000  Depreciation expense  0.000  0.000  0.000  0.000  0.000  0.000  Offset from internal reprioritisation   (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  Sub total (net output price increase)  0.000  0.000  0.000  0.000  0.000  0.000  Offset from revenue   (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  Offset from another funding source  (eg. Commonwealth funding, CSF,  trust account) ‐ please specify   (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  Net Impact on output appropriation  0.000  0.000  0.000  0.000  0.000  0.000  B.4 Revenue  Revenue increase/decrease    2012‐13  $m  2013‐14  $m  2014‐15  $m  2015‐16  $m  2016‐17  $m  Ongoing   $m  Revenue initiative 1  0.000  0.000  0.000  0.000  0.000  0.000  Revenue initiative 2  0.000  0.000  0.000  0.000  0.000  0.000  Less revenue already in  budget/forward estimates   (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  (0.000)  Net revenue impact  0.000  0.000  0.000  0.000  0.000  0.000     22  Department Title    Appendix C: Sign‐off checklist  Investment title:   Agency:  Y/N    Is the need clearly established (e.g. investment concept brief)?     Are the links to government policy(ies) and contributions explicit?     Is there a clear statement of the service benefits and project scope and are future  implications noted?      Are cost estimates provided for capital and operational phases?     Have cost and risk estimators signed off on the adequacy of their work?     Is the project budget including the base cost estimate, risk assessment, base risk  allocation and contingency adequate?      Do cost and benefit estimates and analyses show value for money?     Are the project deliverables clearly stated?     Is a benefit management or evaluation plan included?     Are risk management processes in place and assumptions stated?     Does the proposal assess the project schedule and readiness (including market appetite)?     Are governance structures identified?     Are stakeholder interfaces detailed?     Are regulatory requirements identified?     Is the project High Value/High Risk?     Have Gateway reviews been undertaken?               Gate 1                                                                                              Gate 2   This model checklist is designed for the project proponent’s endorsement.     Prepared by: ……………………………………………..……    Date: …………………    Approved by: ……………………………………………..……   Date: …………………    ……………………………………………...  …………………………………………………….  (name of approving officer or delegate)                     (title)    Secretary: ……………………………………………..……   Date: …………………