MODULE TITLE : BUSINESS MANAGEMENT TECHNIQUES
TOPIC TITLE : PROJECT PLANNING AND SCHEDULING
TUTOR MARKED ASSIGNMENT 5
NAME.......................................................................................................................................
ADDRESS................................................................................................................................
..................................................................................................................................................
..................................................................................................................................................
...................................................... HOME TELEPHONE .....................................................
EMPLOYER.............................................................................................................................
..................................................................................................................................................
..................................................................................................................................................
...................................................... WORK TELEPHONE......................................................
BMT - 5 - TMA (v1)
© Teesside University 2011
THIS BOX MUST BE COMPLETED
Student Code No. ....................................................................................................
Student's Signature ..................................................................................................
Date Submitted ........................................................................................................
Contact e-mail .........................................................................................................
Published by Teesside University Open Learning (Engineering)
School of Science & Engineering
Teesside University
Tees Valley, UK
TS1 3BA
+44 (0)1642 342740
All rights reserved. No part of this publication may be reproduced, stored in a
retrieval system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise without the prior permission
of the Copyright owner.
This book is sold subject to the condition that it shall not, by way of trade or
otherwise, be lent, re-sold, hired out or otherwise circulated without the publisher's
prior consent in any form of binding or cover other than that in which it is
published and without a similar condition including this
condition being imposed on the subsequent purchaser.
IMPORTANT
Before you start please read the following instructions carefully.
1. This assignment forms part of the formal assessment for this module. If
you fail to reach the required standard for the assignment then you will be
allowed to resubmit but a resubmission will only be eligible for a Pass
grade, not a Merit or Distinction.
You should therefore not submit the assignment until you are reasonably
sure that you have completed it successfully. Seek your tutor's advice if
unsure.
2. Ensure that you indicate the number of the question you are answering.
3. Make a copy of your answers before submitting the assignment.
4. Complete all details on the front page of this TMA and return it with
the completed assignment including supporting calculations where
appropriate. The preferred submission is via your TUOL(E) Blackboard
account:
https://eat.tees.ac.uk
5. Your tutor’s comments on the assignment will be posted on Blackboard.
6. Free downloads of Microsoft Project are available from the University
SST website at http/sst.tees.ac.uk. (See next page for instructions.)
1
Teesside University Open Learning
(Engineering)
© Teesside University 2011
Free download of Microsoft Project 2002
You will require your University Student Number (letter followed by 7 digits)
and IT access details, which includes your password, sent to you when you
enrolled on the course.
Go to SST home page at
htpp://sst.tees.ac.uk/
Locate SST Downloads on the left hand menu and underneath this MSDNAA.
Click on this link.
The page will refresh and first brings up a dialogue box and then automatically
goes to the MSDN Academic Alliance software centre. Click log in.
Fill in your Account Number and Password and click log in.
If this is not your first visit to this site, the page will refresh to "My Software".
You should click on "To order new software click here" and then continue as
follows.
On the new page enter Project in the Search box and click on Go.
In the list find Project Professional 2002 and click on it.
On the new screen, click on Add to Cart.
On the new screen click on Checkout.
Fill in your details and click next.
Click on Download and then on the new screen print the page and then click
on Download.
When the dialogue box appears click on save noting where you have saved the
filed to.
After this close the Browser and go the downloaded file.
Click on this and the installation procedure will start. Follow the on-screen
instructions.
2
Teesside University Open Learning
(Engineering)
© Teesside University 2011
(a) State what factors need to be considered when tendering an estimate for a
contract.
(b) Before tendering as a contractor supplying materials and equipment
specified by the client, state briefly some checks that should be made
prior to compiling the tender in order to determine any contract clauses,
contingencies or unforeseen circumstances that may affect future profits.
(c) Prepare a tender/estimate for the installation of 20 steel street lamps in
5 streets of a small town to replace ageing concrete lamp standards, using
the following information.
The holes for the lamp standards have to be excavated using manual
labour. The old concrete lamps need to be removed using a lorry mounted
crane or ‘Hiab’, which also serves as an extendable high platform.
The old lamps are first disconnected by the Supply Authority, which does
not form part of the contract. Removal of old standards to contractor
depot is part to the contract. The new lamp standards consist of the
lanterns (lights) complete with the ballast, ignitor, capacitor and lamp
already fitted. The main materials then are the column, the lantern, the
cable to wire it, a photo-electric cell, tarmas and the concrete. The lamps
are supplied by the contractor to the client’s specification. The lamp
standards have to be erected then concreted (6 metre columns specified
require a 1.3 m buried root depth) then the luminaires/lanterns fixed to the
top and connected to the connection box at the base of the column. In
order to keep the street lighting disruption to a minimum during lamp
standard replacement, arrangements are made with the supply authority to
disconnect old standards and connect the ‘tails’ (i.e. loose cable one end
of which is connected to the lamp standard to be used to connect to the
supply cable) of new standards.
3
Teesside University Open Learning
(Engineering)
© Teesside University 2011
Connection and disconnection by the Supply Authority is not part of the
project tender. This means that the new standards have to be wired ready
for connection. In order to do this holes have to be excavated adjacent to
the old standards to accommodate the new standards and they have to be
concreted with tails brought out before connection can take place.
When connection is complete, the old concrete standards are removed and
temporarily stored for disposal in the contractor’s depot and the holes of
both new and old standards reinstated. Generally the new standards can
be placed within 2 metres adjacent to the old standards.
A mobile crane or ‘Hiab’ lifts the columns and sets them in the holes and
is also used as a platform for working at height. The lanterns, which
contain an infra-red detector for automatic switch-on are pre-wired by the
contractor to avoid damage during installation and are attached at height
using the ‘Hiab’ lorry mounted crane to the columns after column
installation. Cables and wiring are passed from the lantern and threaded
down the column to the connection box at the bottom. The lamp
standards have to be connected at the base connection box by cable ‘tails’
to an existing lighting cable run along the pavement. Identification of
existing underground cables is performed by the Supply Authority and
drawings passed on to the contractor prior to work commencing.
Connection, made by the Supply Authority, is arranged by the client.
Students may assume that the lamps are delivered to the contractor
storage depot and are paid for or enter a cost for purchase and delivery in
their tender.
4
Teesside University Open Learning
(Engineering)
© Teesside University 2011
Students are at liberty to assign their own labour, ordinary and overtime
rates and costs/values for:
• materials, such as concrete, cabling and accessories and paving stone
replacement or tarmac reinstatement
• hire of equipment, such as cranes, HIABs, concrete mixers, etc. or
other hired equipment
• times for excavating and the size of excavations
• cable measuring, cutting, laying, connecting and testing of lantern
and column cable connections prior and post erection
• contractor overheads, including depot security, management, clerical
(wages, etc.) and contract manager’s time compiling tender document
and so on
• any contingencies (e.g. bad weather, vehicle breakdown, vandalism,
strikes, difficult terrain, etc, production of As-Built drawings
detailing position of new lights and connections underground etc, if
any)
• any other contractor costs that the student may consider necessary.
Costs can calculated without considering VAT.
Students should endeavour to use sufficient labour to complete the work
within three to four weeks and without interruption of street lighting
availability.
5
Teesside University Open Learning
(Engineering)
© Teesside University 2011
All assumptions on which the tender is based regarding quantity of labour
and type, duration of manpower employed, times for excavation,
positioning and concreting of new standards, removal of old standards,
etc. should be stated.
Note: There are many options to consider when tendering. For example,
students may opt for excavation of all holes before commencement of
new column installation as this will cut down on the duration of the Hiab
hire. Alternatively students may consider it more profitable for the
contractor to excavate so many holes for old and new standards, then
install the new and remove the old standards before proceeding with more
excavations. It should be remembered that the street lighting has to be
maintained during the replacement of the standards and the Supply
Authority will only disconnect two old and connect two new standards
per day. It is recommended that the best way to execute the contract is to
leave as few excavations open as possible and to leave as many columns
in lighting as possible. Temporary reinstatement usually takes place after
standard positioning and connection and permanent reinstatement of flags
or tarmac in a street will be performed after street completion. If costs
for materials are estimated (for such as paving stones or tarmac, etc.)
allowance should be made for some wastage.
The tender should include labour materials, overheads and contingencies,
and need not include financial arrangements between contractor and
client. As the tender is a preamble to a project plan, these can be
assumed to be interim payments with adjustments and final settlement
and it is not necessary to prepare a cash budget, etc.
Constraints should be recognised, as for example the minimum time the
Hiab will be required will be 2 weeks if it installs 2 new and removes
2 old standards per day. All such modes of working should be clearly
stated and reasons briefly given for the assumptions on which the tender
is costed, for the benefit of the client.
6
Teesside University Open Learning
(Engineering)
© Teesside University 2011
If a contractor has a long term arrangement as preferred contractor with a
local authority or Highways Agency Area, there would usually be a rate
or price agreed at the tender stage for the erection of a new column.
There would also be a number of rates to cover the different lantern types
and column sizes. Alternatively some contractors tender on a ‘cost plus’
basis where the client is charged the material and labour cost plus a
percentage for the contractor’s overheads and profit. This is the form the
student’s tender should take, which requires work activities, amounts of
labour and rates to be specified and the costs of activities, equipment,
contractor’s overheads, etc. to be estimated. From this a project plan
will emerge.
If a tender is pitched too high with profit it may lose out to another
contractor. If too low, it will lose money. It’s a fine line.
(d) A Project plan is required to be prepared for the work tendered for in
part (c) using Microsoft Project 2000 Software, or later, or any other
suitable project software. Notes should accompany the project
assignment describing the details and thinking behind the project form.
The project should show such features as:
• Gantt chart with tasks, dates, bar charts, etc. showing linked tasks
with any lead or lag times
• critical path
• resources list completed
• resources usage
• task usage
7
Teesside University Open Learning
(Engineering)
© Teesside University 2011
• tracking Gantt chart
• resource fixed and task costs
• project % completion and cost report(s)
• tasks that can start simultaneously or prior to the finish of their
predecessor, if any.
Task usage with associated costs (resource and task costs) should be
simulated for the project at 100 % completion and reports produced.
Hard copies of the project assignment are required. CDs or floppy disks
can also be submitted.
It should be noted that the critical path view must be saved as a separate
project or as a screen dump figure pasted into, say, Paint, which is
usually available in Microsoft Office (or Word) Programs/Accessories
on the Start Menu. This is because, if resources are assigned to tasks the
critical path is obscured and shows in normal task colour. Any views that
may be lost in the course of completing the project must be saved at an
appropriate time.
Alternatively students may wish to do a power point presentation of
various views of their project.
8
Teesside University Open Learning
(Engineering)
© Teesside University 2011
It is worth using the first task as a repository for making notes about the
project as one progresses. This is done by selecting Project/Task Notes
which brings up a dialogue box into which can be typed notes and
memos, such as “foreman is not assigned to task (a) because this task is
performed on the same day as task (b) to which the foreman has already
been assigned”, etc.
Leaving the resources dialogue box open and assigning resources will
leave the same resources selected for repetitive tasks, which facilitates
resource assignment. Alternatively, if there are many repetitive tasks, by
holding down the ‘Control’ key each repetitive task can be highlighted
and then by selecting the Assign Resources icon (or Tools/Assign
Resources) and entering the resources data in the dialogue box all the
tasks selected will be updated without having to select each task
individually. This same technique can be applied to task progress
tracking, by holding down the ‘Control’ key each repetitive task can be
highlighted and then by selecting Tools/Tracking/Update Task, and
entering the progress data (e.g. 100 %, actual duration and remaining
duration) all the tasks will be updated without having to select each task
individually.
Assessment will largely be based on the type and quality of the project
program of work execution.
9
Teesside University Open Learning
(Engineering)
© Teesside University 2011