SWINBURNE UNIVERSITY OF TECHNOLOGY
CMS80005 ENGINERING PROJECT CONTROL
ASSIGNMENT 3 FORUM 19 MAY 2017
___________________________________________________________________
Assignment 3 – (50 marks) – Due date – Lecture on 26/5/17.
General Principles:
I ask the questions, you provide the answers
Don’t forget ‘The 6 Honest Men’
Introduction
Project Iron Boomerang (PIB) is a large Australian megaproject that has been proposed by a Queensland company, East West Parks Pty Limited. (See reference below)
Scope of Work
Prelude:
Project Iron Boomerang Video
https://www.youtube.com/watch?v=JGMvy-gDp3U
3,300km single line railway linking the Pilbara in WA and Queensland. Capital Estimate in 2009-US$12.45Billion.
Requires the construction of a series of long length viaducts to cross the numerous floodplains that will be bisected by the new railway along the route.
Viaduct construction:
precast concrete segmental girder sections - 24 and 32m in length
To be ‘cast in situ’ in on site casting plant located at each viaduct site
transported and supported on 6m or 10m height bridge piers using a ‘bridge girder erection’ vehicle
Viaduct piers will also be constructed using precast concrete sections that are located on 30m depth bored pile footings.
Key consideration is time taken to build the viaduct because of the impact of wet season (November to April) on construction.
Assume that all necessary earthworks for the railway will have been completed prior to any work commencing on the viaducts.
TABLE – VIADUCT OPTIONS – for each student
Viaduct Type No.: Viaduct Length (m) Span of Girder between piers (m) Height of pier from - ground level to girder underside (m) The last digit of your enrolment number
1 1920 32 6 1,2
2 1920 24 7 3,4,5
3 1920 32 8 6,7
4 1920 24 9 8,9,0
Note: Which Option do I do? Use the last digit of your Swinburne Enrolment Number and refer to the last column of the Table above.
Question 1
Definitions – 4 marks
Linear Project
Time Chainage Diagram
Question 2
Time-Chainage Diagram (TCD) - Viaduct – 15 marks
Requirements:
Start date of 1 January 2020
TCD in AutoCAD, XL or other graphical software
Show all activities to be undertaken for the construction of the viaduct
Activities to include:
site establishment
building a casting yard
casting of the viaduct segments
Prestressed / Precast Plant Tour Part 1 of 2
https://www.youtube.com/watch?v=HLnV-fdf9kQ
(accessed 28 April 2017)
construction plant/equipment set up
Continuous Flight Auger Piling Method
www.youtube.com/watch?v=LNGAP0iZ8YU
(accessed 28 April 2017)
‘Bridge girder erection machine: SLJ900’
https://www.youtube.com/watch?v=vKGYs71N72c (
accessed 10/2/17)
Type I Full Span Launching 820Ton Box Girder
www.youtube.com/watch?v=-t99Ns8Hoxo
In your answer:
Include all assumptions
Include calculations for estimating construction activity durations.
Show start date and finish date for the work
Detail on your TCD the start and finish date for the works
Construction work will be undertaken on a 6-day week basis
Which Option do you do:
Viaduct Type No.: Viaduct Length (m) Span of Girder between piers (m) Height of pier from - ground level to girder underside (m) The last digit of your enrolment number
1 1920 32 6 1,2
2 “ 24 7 3,4,5
3 “ 32 8 6,7
4 “ 24 9 8,9,0
Note: Which Option do I do? Use the last digit of your Swinburne Enrolment Number and refer to the last column of the Table above.
Question 3
Prepare a Construction Method Statement – 10 Marks
Outline the steps involved in the construction of all aspects of your viaduct
Include a detailed list of construction plant and equipment that would be utilised on the project
Provide details of the hazards and risks involved in the project with particularly with the use of:
SLI900 ‘bridge girder erection machine’
Crane/s for erection of the precast concrete units for each of the piers.
Question 4
Tracking of project commodities for construction ‘progress’ control – 8 marks
Asked to track earthworks volumes, crushed rock and ballast stockpiles, quantities of rail and sleepers and viaduct construction.
By reference to the paper (see below) by Birenza RM and Hildreth JC outline how this could be undertaken.
Question 5
UAV’s – 6 marks
Asked how we could track project commodities by using aerial drones or UAV’s to assess construction progress over the route of the railway.
Outline how drones etc could be used for aiding the tracking of the above, together with the amount of rail track that has been laid at various points in the contract.
Question 6
Long Lead Item supply – 6 Marks
Define long lead items
What procedures would you put in place to ensure that the OEM’s meet specified requirements and supply items are delivered to site on time?
References and useful material:
Arup Sustainability, Appendix D, Construction Method Statement
http://www.ugdc.nsw.gov.au/sites/default/files/file_root/PDFs/Precincts/Redfern_Waterloo/North_eveleigh_bridge/Appendicies/Appendix%20D%20Construction%20Method%20Statement.pdf
Brienza RM, Hildreth JC, ‘Tracking Project Commodities for Project Control’, VDOT-VT Partnership for Project Scheduling, Charles Edward Via, Jr. Department of Civil and Environmental Engineering, Virginia Tech, December 2007
Rohleder WJ, Segmental Bridge Technology – Established and Evolving, University at Buffalo, State University of New York, 2011.
http://mceer.buffalo.edu/education/bridge_speaker_series/2010-2011/presentations/Rohleder_presentation.pdf
Rosignoli M, ‘Full-span precasting for light-rail transit and high-speed railway bridges, Prestressed Concrete Institute Journal, USA, Spring 2014
Rosignoli M, ‘Modena viaducts for Milan–Naples high-speed railway in Italy. Prestressed Concrete Institute Journal, USA, Fall 2012.
Time Chainage reporting made easy, http://www.pcfltd.co.uk/products/linearplus/ (accessed 10/2/17)