Development and Implementation of an E-Procurement System for MV
Cost baseline & fund requirement
Version Number: 1.0
Version Date: 05/07/2017
Student’s name:
Student’s Number:
Tutor Name:
COST BASELINE
Activities April'17 May'17 June'17 July'17 August'17 September'17 October'17 November'17 December'17 January'18 February'18 March'18 April'18
1. Development and Implementation of an E-Procurement System for MV
1.1. Project management
1.1.1. Project management Plan 1,500 3,500
1.1.2. Project Schedule 3,355
1.2. Technical design
1.2.1. Design database management 2,500
1.2.2. Design screen 7,167 7,167 7,167
1.2.3. Design confirmation 1,064
1.3. Implementation
1.3.1. Execution of software loading 7,000
1.3.2. Installation of required hardware 8,806 8,806 8,806
1.3. Testing
1.3.1. Design checklist 4,500
1.3.2. Acceptance by client 4,500
1.3.3. Go live 7,710
Monthly Total 1,500 6,855 2,500 7,167 7,167 7,167 1,064 7,000 8,806 8,806 8,806 4,500 12,210
Cumulative Total 1,500 8,355 10,855 18,022 25,188 32,355 33,419 40,419 49,225 58,032 66,838 71,338 83,548
FUNDING REQUIREMENTS
Project Gates Funds Required
(in AUD)
Project Management activities over 8,355.00
Confirmation of Technical design 25,064.00
Implementation over 33,419.00
Testing of the system done & Go Live 16,710.00
Management Reserve (at 25% of Baseline Cost) 20,887.00
Total Funding Requirement 104,435.00