Project Plan Marking Grid
Criterion <30 30+ 40+ 50+ 60+ 70+
Project Scope & Product Management (25%) No definition of the project Attempt made to describe scope, no Product Breakdown Structure (PBS) Fair description of Project Scope, PBS incomplete and no products described (or described poorly) Good description of Project Scope,
PBS presented with more than 20 appropriate products
but no products described or described poorly Well defined project scope,
complete PBS with more than 40 appropriate products,
product description/s presented but incomplete Excellent project scope,
complete PBS with more than 60 appropriate products,
complete description/s of at least 3 products.
Feasibility and Business Case (10%) Wildly impossible with no thought into implementation issues.
No business case elements presented to an acceptable standard The idea may be practically impossible for the team to execute. Little thought has gone into implementation issues.
Does not complete at least 3 of the following Business Case elements to an acceptable standard:
The business option selected and alternatives considered
Primary and any secondary objective(s)
Expected benefits and Estimated Total costs and Resources required
Stakeholder Analysis
Constraints and assumptions
Completion date + milestones
Key project personnel and roles The Project Team has done little research/ verification and there may be significant implementation issues.
Completes at least 3 of the following Business Case elements to an acceptable standard:
The business option selected and alternatives considered
Primary and any secondary objective(s)
Expected benefits and Estimated Total costs and Resources required
Stakeholder Analysis
Constraints and assumptions
Completion date + milestones
Key project personnel and roles The Project Team has done limited research/ verification and there may be possible implementation issues not considered.
Completes the following Business Case elements and at least 2 to a high standard:
The business option selected and alternatives considered
Primary and any secondary objective(s)
Expected benefits and Estimated Total costs and Resources required
Stakeholder Analysis
Constraints and assumptions
Completion date + milestones
Key project personnel and roles The Project Team has only done some research/ verification but there still remain a few doubts about the ability of the team to carry out the idea.
Good Business Case but the justification for 1 or 2 of the following elements may not be clear:
Why the business option was selected and alternatives considered
Primary and any secondary objective(s)
Expected benefits and Estimated Total costs and Resources required
Stakeholder Analysis
Constraints and assumptions
Completion date + milestones
Key project personnel and roles The Project Team has done a good degree of research/ verification which gives confidence that the idea can be carried out by this team.
The Business Case is Comprehensive, believable and logical with good use of PM theory and concepts.
Completes the following to a high standard:
Why the business option was selected and alternatives considered
Primary and any secondary objective(s)
Expected benefits and Estimated Total costs and Resources required
Stakeholder Analysis
Constraints and assumptions
Completion date + milestones
Key project personnel and roles
Criterion <30 30+ 40+ 50+ 60+ 70+
Project Time Management (30%) Nothing acceptable with respect to:
Work Breakdown Structure,
Activity List,
Gannt Chart
Network Diagram. Weak attempts made to at least 2 of the following:
Work Breakdown Structure,
Activity List,
Gannt Chart
Network Diagram. One of the following completed to an acceptable standard, weak attempts at the rest:
Work Breakdown Structure,
Activity List,
Gannt Chart
Network Diagram. Two of the following completed to an acceptable standard, weak attempts at the rest:
Work Breakdown Structure,
Activity List,
Gannt Chart
Network Diagram must have at least 5 parallel paths. Two of the following elements completed to a high standard, the rest are done to an acceptable standard:
Work Breakdown Structure,
Activity List,
Gannt Chart
Network Diagram must have at least 12 parallel paths. The following are all completed to a high standard:
Work Breakdown Structure,
Activity List,
Gannt Chart
Network Diagram must have at least 20 parallel paths.
Project Communication Management (15%) Work of no merit given for this part of the assignment Stakeholders identified only Stakeholders identified and needs analyzed Stakeholders identified, needs analysed and communication content identified Stakeholders identified, needs analysed, communication content and frequency specified Stakeholders identified, needs analysed, communication content and frequency specified, evidence of use (eg, communications activities included in WBS/Schedule)
Project Risk Management (15%) Work of no merit given for this part of the assignment An attempt made at identifying risks Risks identified, initial analysis conducted. Risks identified and analysed, attempt made at planning responses. Satisfactory risk register Risks identified and analysed, detailed responses planned. Good risk register. Risks identified and analysed, detailed responses planned, proximity of risks identified. Excellent risk register.
Project Quality Management (5%) Work of no merit given for this part of the assignment An attempt made at identifying Quality criteria and tests but poorly done. Quality criteria and tests identified for a few project products and schedule of tests planned…many errors or omissions Quality criteria and tests identified for a few project products and schedule of tests planned Detailed quality criteria and tests identified for main project products and schedule of tests planned…minor errors Detailed quality criteria and tests identified for main project products and schedule of tests planned.