Assignment title: Information
ASSIGNMENT 2016
Question 1 – 30 marks
b)
An Asian Pacific capital city proposes to design, construct and operate a new
double track railway from the city to connect to its major airport. Prefeasibility
studies that included geotechnical engineering investigations considers that
ground conditions are such that the double track railway will need to be
constructed both at grade or be elevated on a viaduct as detailed below for the
various lengths of line:
Chainage:
0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade
Construction time estimates have been prepared for Stage 1 of the project which
will consist of the construction of the viaduct section of the line from 3km to
10km. (An example of a recently completed similar project is on a new high
speed railway from Erfurt to Leipzig/Halle in Germany – the 'Saale-Elster Viaduct
which is 6.5km in length – reference below).
Following completion of the viaduct section a separate contract will be let for the
installation of the track components where it is proposed to use
prefabricated/precast concrete slab track sections (PCSTS) that will be erected in
sections for each of the two tracks. For the purpose of analysis, the FFB Slab
Track 'Bogl' system that has been used successfully in Germany and China will be
considered.
It will be necessary to construct PCSTS fabrication plant/s located at a strategic
point/s along the length of the viaduct section of the route. Fabrication plant/s of
modular construction will take an estimated 3 months to construct and
commission and be ready to produce the PCSTS sections. Work on this activity
will need to start at contract commencement following a 1-month period of
mobilization by the contractor.
Each modular plant should be capable of producing an estimated 75 off, PCSTS
sections per day of operation. The PCSTS sections are to be stockpiled at the
fabrication plant after manufacture for 2 months prior to the track laying
operation on the viaduct commencing.
Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point)
on special flat wagon trains, to complete the track laying operation, and once
installed will need to be site welded to ensure that there is continuous welded rail
installed over the whole length of the route. It is assumed that on grade sections
of line will have been completed and track laid.
On each side of the proposed viaduct route it will be possible to construct
vehicular access tracks except for the estuary section that will be over water i.e.
no roads can be built.
b1. Prepare a step-by- step, detailed methodology for how you would
propose to construct the double line of track work for the length of
the viaduct. Include a list of construction plant and equipment that
will be needed for the operation. (6 marks)
b2. Prepare a construction schedule for the track installation contract
on the viaduct (commencing at the 3km point) in Time-Chainage
Diagram (TCD) format using XL or AutoCAD or other graphical
means showing all activities that need to undertaken for the
construction of the double line track including site establishment,
and equipment set up. Include all assumptions and calculations for
estimating construction duration. (12 marks)
b3. Prepare a second TCD, assuming that construction activity is
undertaken from the 3km and the 10km simultaneously. Include
all assumptions and calculations for estimating construction
durations. (6 marks)
b4. Prepare a Safe Work Method Statement (SWMS) or JSA for the
lifting equipment that would be used on the viaduct including
working at height.
(6 marks)
Useful Material:
For students who maybe unfamiliar with modern concrete viaduct structures:
Rohleder WJ, Segmental Bridge Technology – Established and Evolving, University
at Buffalo, State University of New York, 2011.
http://mceer.buffalo.edu/education/bridge_speaker_series/2010-
2011/presentations/Rohleder_presentation.pdf
References:
'The Saale-Elster Viaduct project'
http://www.vde8.de/The-Saale- Elster-Viaduct- project-- -- --
_site.site..ls_dir._siteid.373_function.set__lang_lang.en_likecms.html
Amberg Technologies, Project Report GRP1000, Slab Track 'Made in China',
Olympic High Speed Line Beijing-Tianjin, (accessed 10/2/16).
http://max-boegl.de/fileadmin/content/download-
center/produktbroschueren/EN/Produktbroschueren_EN_FFB_Feste_Fahrbahn_Boegl.p
df
http://wenku.baidu.com/view/8213e5e8f8c75fbfc77db213 (accessed 10/2/16)
'Slab Track China' FFB Max Bogl (accessed 10/2/16).
http://max-boegl.de/fileadmin/content/download-
center/projektbroschueren/EN/C_EN_Feste_Fahrbahn_China.pdf