Assignment title: Information
SIT374 / SIT764: Project Management Assignment 2
Due: 11:59pm, Friday 20 May.
Worth: 20% - Two questions, 10 marks each
Note: SIT764 students will be marked independently of the SIT374 students based on different
assessment criteria, and are required to detail your explanations and present your work as though you
were reporting to management.
Question 1 (10 marks)
Your company is doing well and has a profit of about $50,000. You want to make your profit work
harder so you have looked at some investment opportunities available. They are
To insulate the current company offices at a cost of $18,000 which will provide a fuel savings
of $1,600 per year over the next 10 years.
To pay the lump sum of $30,000 to the mortgage of $40,000 that has a loan term of 10 years
at 6.5% interest per annum.
To invest $20,000 into a new business, which has been estimated to return the double amount
in 6 years' time.
To keep the profit $50,000 in an iSaver account earning a fixed interest of 4.5% per annum for
8 years. After 8 years, there will be no interest for this iSaver account.
Assumptions:
- If only a part of the profit $50,000 is invested in a project, the remaining amount is still kept in
the pocket (i.e. no investment).
- The investment/cost occurs at the beginning of a year, and the investment benefits are
obtained at the end of a year.
- iSaver account calculates the compound interest.
(a) Given the profit you have and assuming a discount rate of 4.8%, perform and document
appropriate NPV calculations for 10 years for all possible investment options you identified. Graph
the results to show the payback analysis of each investment option.
You must use Microsoft Excel or an equivalent spreadsheet program to perform and present your
calculations.
Do not use the Excel NPV function and demonstrate you understand the formulas by calculating
the NPV. You may confirm the calculated NPV using the Excel NPV function.
Ensure you format the spreadsheets so they use references rather than hard coding data. This
allows experimenting with the data, e.g., if I change the discount rate the data should react and
change accordingly.
Use bolding, colors etc. to ensure the data is easy to interpret.
(b) From your calculations in (a), which investment would you take up and why?
Use a Weighted Scoring Model (see an example on pages 154-155 of the textbook) to discuss the
results and explain in detail why you have chosen one option over the others. It is not always just
the figures that determine the final decision.
Create a report in Word or PDF format to present the outcomes of (a) and (b). Use the data,
graphs etc. created within the spread sheet program to present the outcomes.
Question 2 (10 marks)
You are in charge of building a new office for your company. After some discussion with your builder,
you identified some of the key tasks, the duration and the costs to complete the building. As you are a
project manager you have decided to monitor the building progress using Earned Value Management
(EVN). Answer the following questions using the following information
D Task Name Cost ($) Start Date Duration
1 Lay foundations 18,000 November 1 2 weeks
2 Build frame 34,000 November 4 weeks
3 Install pipes and electrical 10,000 December 6 weeks
4 Make office water-tight 15,000 February 8 weeks
5 Install internal walls and bathroom 20,000 April 12 weeks
6 Install cabinetries 14,000 July 4 weeks
7 Paint office 8,000 August 2 weeks
8 Install light fixtures and appliances 9,000 August 2 weeks
NOTE: Assume that no task is scheduled to run concurrently, e.g., Task 2 starts after Task 1
completes, Task 3 starts only when Task 2 completes, and so on. Also, assume that each month is
made up of exactly four weeks.
(a) What is the planned value of the entire project?
(b) The project manager has managed to keep cost to what was originally budgeted above. At
this point, the project has completed Task 4. Up to this point,
i. What is the planned value of the project?
ii. What is the actual cost (AC) of the project? Briefly explain how you derive the actual
cost.
iii. What is the rate of performance (RP) for each task? Using the RPs obtained,
calculate the Earned Value (EV), Schedule Variance (SV), Cost Performance Index
(CPI), and Schedule Performance Index (SPI) of the project.
(c) Unfortunately, two trades resigned after Task 5 was completed and this caused the remaining
tasks to exceed its original cost and schedule by 25%, 30%, 40% respectively. At the end of
the project,
i. What are the CPI and SPI?
ii. How is the performance with respect to cost and time?
iii. Represent the Planned Value (PV), Earned Value (EV) and Actual Cost (AC) in a
chart like the example below.
**** Example only ****
Submission Requirements:
- Microsoft Excel or equivalent files showing all calculation details, and
- Corresponding reports in Word or PDF format explaining your calculations and conclusions.
Resources which could be used include
Textbook (very important)
Workshop materials on CloudDeakin
Lecture notes and useful resources on CloudDeakin
Related materials on the Web
Note particularly that reproducing someone else's work is not permitted. It may be very valuable
though to reference and comment on the differences between various works which you find. While you
are welcome to collaborate with your fellow classmates, you cannot forward your work onto somebody
else, allow somebody else to copy from your own work, and most important any work submitted must
be entirely your own.
Your attention is drawn to the Plagiarism Statement on CloudDeakin. Anyone using cut-and- paste or
copying other people's work will be easily detected; the outcome is a disciplinary committee hearing
and an automatic zero for the assignment. No excuses.
There is no page number limitation for this assignment. But irrelevant materials should not be
included. Please note an assignment longer in length DOES NOT mean a higher mark you will get.
Remember: if the assignment marker can't find the answer, then you will not get the mark for it. Make
it easy to understand.
Appropriate referencing should be done. However, do not provide a reference for every separate
fact.
The assignment must be submitted to CloudDeakin before or on the due date. Late submission will
lead to a mark penalty or not being assessed (for more details, please read the Unit Guide on
CloudDeakin carefully).
If you wish to apply for an extension, application should be submitted to the unit chair before the due
date. Documentary evidence of the disadvantage causing this request, and an ongoing assignment
representing the work you have completed are expected to be submitted. A judgement will be made
by the unit chair as to whether an extension shall be granted.